Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Tennessee |
---|---|
Assessment Year | 1984 |
Principal Product | JACKETS & OUTERWEAR |
NAICS | n/a |
SIC | 2337 - Women's, Misses', and Juniors' Suits, Skirts, and Coats |
Sales | $5,000,000-$10,000,000 |
# of Employees | 310 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 1,300,000 Pieces |
Production Hrs. Annual | 2,285 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $97,579 | 1,594,373 | kWh | $0.06 |
Natural Gas | $17,813 | 3,390 | MMBtu | $5.25 |
TOTAL ENERGY COSTS | $115,392 | |||
RECOMMENDED SAVINGS* | $7,200 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $6,590 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $5,160 Cost: $10 |
$5,160 | 128,957 | - | - |
$5,160 128,957 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,336 Cost: $2,325 |
$1,336 | 33,411 | - | - |
$1,336 33,411 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $610 Cost: $2,500 |
$610 | 15,240 | - | - |
$610 15,240 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2122 INSTALL / REPAIR INSULATION ON CONDENSATE LINES |
Savings: $94 Cost: $45 |
- | - | $94 | 18 |
- - kWh |
$94 18 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $7,200 Cost: $4,880 |
$7,106 | 177,608 | $94 | 18 | $7,106 177,608 kWh |
$94 18 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $6,590 Cost: $2,380 |
$6,496 | 162,368 | $94 | 18 | $6,496 162,368 kWh |
$94 18 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |