Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Tennessee |
---|---|
Assessment Year | 1986 |
Principal Product | REAR VIEW TRUCK MIRRORS |
NAICS | n/a |
SIC | 3231 - Products Of Purchased Glass |
Sales | $10,000,000-$50,000,000 |
# of Employees | 285 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 3,000,000 Pieces |
Production Hrs. Annual | 6,000 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $256,095 | 5,325,616 | kWh | $0.05 |
Natural Gas | $118,999 | 22,659 | MMBtu | $5.25 |
TOTAL ENERGY COSTS | $375,094 | |||
RECOMMENDED SAVINGS* | $22,315 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $13,650 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7492 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE |
Savings: $7,812 Cost: $25,175 |
- | - | $7,812 | 1,474 |
- - kWh |
$7,812 1,474 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $6,477 Cost: $2,580 |
- | - | $6,477 | 1,222 |
- - kWh |
$6,477 1,222 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $2,236 Cost: - |
- | - | $2,236 | 422 |
- - kWh |
$2,236 422 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6221 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY |
Savings: $3,601 Cost: - |
$3,601 | 75,029 | - | - |
$3,601 75,029 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $853 Cost: $596 |
- | - | $853 | 161 |
- - kWh |
$853 161 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,336 Cost: $260 |
$1,336 | 27,843 | - | - |
$1,336 27,843 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $22,315 Cost: $28,611 |
$4,937 | 102,872 | $17,378 | 3,279 | $4,937 102,872 kWh |
$17,378 3,279 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $13,650 Cost: $2,840 |
$4,937 | 102,872 | $8,713 | 1,644 | $4,937 102,872 kWh |
$8,713 1,644 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |