Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Tennessee |
---|---|
Assessment Year | 1987 |
Principal Product | INDUSTRIAL VALVES |
NAICS | n/a |
SIC | 3491 - Industrial Valves |
Sales | $10,000,000-$50,000,000 |
# of Employees | 230 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 83,000 Pieces |
Production Hrs. Annual | 6,120 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $263,326 | 5,101,993 | kWh | $0.05 |
Natural Gas | $64,761 | 14,112 | MMBtu | $4.59 |
LPG | $7,650 | 1,035 | MMBtu | $7.39 |
TOTAL ENERGY COSTS | $335,737 | |||
RECOMMENDED SAVINGS* | $30,173 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $24,565 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | LPG | Electricity Usage | Natural Gas | LPG | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $3,984 Cost: $300 |
- | - | $3,984 | 866 | - | - |
- - kWh |
$3,984 866 MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $4,339 Cost: $2,160 |
- | - | $3,018 | 655 | $1,321 | 178 |
- - kWh |
$3,018 655 MMBtu |
$1,321 178 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $3,432 Cost: $1,442 |
- | - | $3,432 | 746 | - | - |
- - kWh |
$3,432 746 MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $8,072 Cost: $960 |
$8,072 | 158,265 | - | - | - | - |
$8,072 158,265 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $1,918 Cost: $4,980 |
- | - | $1,918 | 417 | - | - |
- - kWh |
$1,918 417 MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $2,024 Cost: $6,761 |
- | - | $1,408 | 306 | $616 | 83 |
- - kWh |
$1,408 306 MMBtu |
$616 83 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,749 Cost: - |
$1,749 | 34,291 | - | - | - | - |
$1,749 34,291 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4312 IMPROVE LUBRICATION PRACTICES |
Savings: $1,666 Cost: - |
$1,666 | 32,532 | - | - | - | - |
$1,666 32,532 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,989 Cost: $600 |
$2,989 | 58,617 | - | - | - | - |
$2,989 58,617 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $30,173 Cost: $17,203 |
$14,476 | 283,705 | $13,760 | 2,990 | $1,937 | 261 | $14,476 283,705 kWh |
$13,760 2,990 MMBtu |
$1,937 261 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $24,565 Cost: $5,462 |
$12,810 | 251,173 | $10,434 | 2,267 | $1,321 | 178 | $12,810 251,173 kWh |
$10,434 2,267 MMBtu |
$1,321 178 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | LPG | Electricity Usage | Natural Gas | LPG |