Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Tennessee |
---|---|
Assessment Year | 1989 |
Principal Product | BOOTS,VULCANIZ. PRESSES |
NAICS | n/a |
SIC | 3143 - Men's Footwear, Except Athletic |
Sales | $10,000,000-$50,000,000 |
# of Employees | 265 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 592,000 Pieces |
Production Hrs. Annual | 6,000 |
Location (State) | NC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $175,418 | 3,526,964 | kWh | $0.05 |
Fuel Oil #2 | $18,190 | 2,996 | MMBtu | $6.07 |
TOTAL ENERGY COSTS | $193,608 | |||
RECOMMENDED SAVINGS* | $26,952 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $11,821 |
#|Description |
Savings Cost |
Status | Electricity Usage | Fuel Oil #2 | Administrative Changes | Electricity Usage | Fuel Oil #2 | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7123 KEEP LAMPS AND REFLECTORS CLEAN |
Savings: $10,266 Cost: $24,045 |
$9,906 | 198,124 | - | - | $360 | - |
$9,906 198,124 kWh |
- - MMBtu |
$360 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7133 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE |
Savings: $4,620 Cost: $1,150 |
$4,620 | 92,321 | - | - | - | - |
$4,620 92,321 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $4,865 Cost: $1,211 |
$4,865 | 97,304 | - | - | - | - |
$4,865 97,304 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2163 USE MINIMUM STEAM OPERATING PRESSURE |
Savings: $1,135 Cost: - |
- | - | $1,135 | 187 | - | - |
- - kWh |
$1,135 187 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,550 Cost: $600 |
$2,550 | 50,996 | - | - | - | - |
$2,550 50,996 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $1,685 Cost: $1,700 |
$1,685 | 33,705 | - | - | - | - |
$1,685 33,705 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $703 Cost: - |
$703 | 14,068 | - | - | - | - |
$703 14,068 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,128 Cost: $900 |
$1,128 | 22,567 | - | - | - | - |
$1,128 22,567 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $26,952 Cost: $29,606 |
$25,457 | 509,085 | $1,135 | 187 | $360 | - | $25,457 509,085 kWh |
$1,135 187 MMBtu |
$360 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $11,821 Cost: $4,350 |
$10,686 | 213,657 | $1,135 | 187 | - | - | $10,686 213,657 kWh |
$1,135 187 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Fuel Oil #2 | Administrative Changes | Electricity Usage | Fuel Oil #2 | Administrative Changes |