Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Tennessee |
---|---|
Assessment Year | 1991 |
Principal Product | DENIM PANTS |
NAICS | n/a |
SIC | 2325 - Men's and Boys' Separate Trousers and Slacks |
Sales | $10,000,000-$50,000,000 |
# of Employees | 170 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 4,800,000 Pieces |
Production Hrs. Annual | 2,880 |
Location (State) | KY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $54,870 | 815,358 | kWh | $0.07 |
LPG | $17,394 | 1,858 | MMBtu | $9.36 |
TOTAL ENERGY COSTS | $72,264 | |||
RECOMMENDED SAVINGS* | $9,165 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $9,165 |
#|Description |
Savings Cost |
Status | Electricity Usage | LPG | Administrative Changes | Electricity Usage | LPG | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $5,675 Cost: $2,700 |
$5,675 | 84,701 | - | - | - | - |
$5,675 84,701 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $1,089 Cost: $1,590 |
- | - | $1,089 | 116 | - | - |
- - kWh |
$1,089 116 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6222 USE DRYING OVEN (BATCH TYPE) ON ALTERNATE DAYS OR OTHER OPTIMUM SCHEDULE TO RUN EQUIPMENT WITH FULL LOADS |
Savings: $507 Cost: - |
- | - | $507 | 54 | - | - |
- - kWh |
$507 54 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $488 Cost: $165 |
- | - | $488 | 52 | - | - |
- - kWh |
$488 52 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7123 KEEP LAMPS AND REFLECTORS CLEAN |
Savings: $1,068 Cost: - |
$1,021 | 15,240 | - | - | $47 | - |
$1,021 15,240 kWh |
- - MMBtu |
$47 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $338 Cost: $859 |
- | - | $338 | 36 | - | - |
- - kWh |
$338 36 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $9,165 Cost: $5,314 |
$6,696 | 99,941 | $2,422 | 258 | $47 | - | $6,696 99,941 kWh |
$2,422 258 MMBtu |
$47 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $9,165 Cost: $5,314 |
$6,696 | 99,941 | $2,422 | 258 | $47 | - | $6,696 99,941 kWh |
$2,422 258 MMBtu |
$47 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | LPG | Administrative Changes | Electricity Usage | LPG | Administrative Changes |