Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Tennessee |
---|---|
Assessment Year | 1994 |
Principal Product | Sealants and Adhesives |
NAICS | n/a |
SIC | 2891 - Adhesives And Sealants |
Sales | $50,000,000-$100,000,000 |
# of Employees | 216 |
Plant Area (Sq.Ft.) | 203,500 |
Annual Production | 210,000 Thousand Feet |
Production Hrs. Annual | 6,240 |
Location (State) | KY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $481,008 | 10,936,987 | kWh | $0.04 |
Natural Gas | $122,559 | 22,818 | MMBtu | $5.37 |
TOTAL ENERGY COSTS | $603,567 | |||
RECOMMENDED SAVINGS* | $33,193 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $31,309 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2113 REPAIR OR REPLACE STEAM TRAPS |
Savings: $17,076 Cost: $780 |
- | - | $17,076 | 3,162 |
- - kWh |
$17,076 3,162 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $6,276 Cost: $585 |
$5,120 | 116,354 | $1,156 | 214 |
$5,120 116,354 kWh |
$1,156 214 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,540 Cost: $1,786 |
$2,540 | 57,737 | - | - |
$2,540 57,737 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $2,076 Cost: $480 |
$2,076 | 47,186 | - | - |
$2,076 47,186 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $1,625 Cost: - |
$1,625 | 36,928 | - | - |
$1,625 36,928 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,613 Cost: - |
$1,613 | 36,635 | - | - |
$1,613 36,635 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,548 Cost: $510 |
$1,548 | 35,170 | - | - |
$1,548 35,170 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $271 Cost: $915 |
$271 | 6,155 | - | - |
$271 6,155 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $168 Cost: $345 |
$168 | 3,810 | - | - |
$168 3,810 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $33,193 Cost: $5,401 |
$14,961 | 339,975 | $18,232 | 3,376 | $14,961 339,975 kWh |
$18,232 3,376 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $31,309 Cost: $4,486 |
$13,077 | 297,185 | $18,232 | 3,376 | $13,077 297,185 kWh |
$18,232 3,376 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |