Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Tennessee |
---|---|
Assessment Year | 1996 |
Principal Product | Metal Indoor Furniture |
NAICS | n/a |
SIC | 2519 - Household Furniture, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 152 |
Plant Area (Sq.Ft.) | 50,000 |
Annual Production | 55,000 Pieces |
Production Hrs. Annual | 2,168 |
Location (State) | NC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $19,728 | 437,280 | kWh | $0.05 |
Electricity Demand | $21,757 | 2,515 | kW-months/year | $8.65 |
LPG | $57,213 | 7,586 | MMBtu | $7.54 |
TOTAL ENERGY COSTS | $103,258 | |||
RECOMMENDED SAVINGS* | $26,574 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $14,580 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Fuel Oil #2 | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Fuel Oil #2 | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3192 USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS |
Savings: $14,000 Cost: $65,000 |
- | - | - | - | $(-2,500) | (-614) | - | - | $(-2,500) | - | $19,000 | - |
- - kWh |
- - kW-months/year |
$(-2,500) (-614) MMBtu |
- - lb |
$(-2,500) - $ |
$19,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4325 UPGRADE CONVEYORS |
Savings: $9,029 Cost: $10,700 |
$(-79) | (-1,758) | $(-72) | (-12) | - | - | - | - | $9,180 | - | - | - |
$(-79) (-1,758) kWh |
$(-72) (-12) kW-months/year |
- - MMBtu |
- - lb |
$9,180 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $2,596 Cost: $7,980 |
$(-50) | (-1,172) | - | - | - | - | $2,696 | 351,669 | $(-50) | - | - | - |
$(-50) (-1,172) kWh |
- - kW-months/year |
- - MMBtu |
$2,696 351,669 lb |
$(-50) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6211 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES |
Savings: $369 Cost: $430 |
$369 | 8,206 | - | - | - | - | - | - | - | - | - | - |
$369 8,206 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2531 RE-SIZE CHARGING OPENINGS OR ADD MOVABLE COVER OR DOOR |
Savings: $203 Cost: $560 |
$203 | 7,913 | - | - | - | - | - | - | - | - | - | - |
$203 7,913 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $195 Cost: $140 |
$92 | 2,052 | $103 | 12 | - | - | - | - | - | - | - | - |
$92 2,052 kWh |
$103 12 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $182 Cost: - |
$79 | 1,758 | $103 | 12 | - | - | - | - | - | - | - | - |
$79 1,758 kWh |
$103 12 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $26,574 Cost: $84,810 |
$614 | 16,999 | $134 | 12 | $(-2,500) | (-614) | $2,696 | 351,669 | $6,630 | - | $19,000 | - | $614 16,999 kWh |
$134 12 kW-months/year |
$(-2,500) (-614) MMBtu |
$2,696 351,669 lb |
$6,630 - $ |
$19,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $14,580 Cost: $65,700 |
$374 | 11,723 | $206 | 24 | $(-2,500) | (-614) | - | - | $(-2,500) | - | $19,000 | - | $374 11,723 kWh |
$206 24 kW-months/year |
$(-2,500) (-614) MMBtu |
- - lb |
$(-2,500) - $ |
$19,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Fuel Oil #2 | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Fuel Oil #2 | Solid Waste (non-haz) | Personnel Changes | Administrative Changes |