Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Tennessee |
---|---|
Assessment Year | 1996 |
Principal Product | Packaged country hams |
NAICS | n/a |
SIC | 2013 - Sausages And Other Prepared Meats |
Sales | $5,000,000-$10,000,000 |
# of Employees | 55 |
Plant Area (Sq.Ft.) | 28,000 |
Annual Production | 4,000,000 Pounds |
Production Hrs. Annual | 2,340 |
Location (State) | NC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $22,230 | 1,246,776 | kWh | $0.02 |
Electricity Demand | $9,685 | 1,116 | kW-months/year | $8.68 |
TOTAL ENERGY COSTS | $34,016 | |||
RECOMMENDED SAVINGS* | $160,873 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $34,594 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Raw Material | By-product Production | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Raw Material | By-product Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.321 OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES |
Savings: $92,395 Cost: $100,000 |
- | - | - | - | - | - | $(-7,605) | - | - | - | - | - | $100,000 | - |
- - kWh |
- - kW-months/year |
- - lb |
$(-7,605) - $ |
- - $ |
- - $ |
$100,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4325 UPGRADE CONVEYORS |
Savings: $30,420 Cost: $14,000 |
- | - | - | - | - | - | $30,420 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - lb |
$30,420 - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.5313 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE |
Savings: $25,513 Cost: $10,000 |
- | - | - | - | $23,721 | 197,600 | - | - | $1,792 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$23,721 197,600 lb |
- - $ |
$1,792 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 4.211 CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE |
Savings: $6,872 Cost: $25,000 |
- | - | - | - | $375 | 469 | - | - | - | - | $6,497 | - | - | - |
- - kWh |
- - kW-months/year |
$375 469 lb |
- - $ |
- - $ |
$6,497 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $2,668 Cost: - |
$1,021 | 24,912 | $1,647 | 192 | - | - | - | - | - | - | - | - | - | - |
$1,021 24,912 kWh |
$1,647 192 kW-months/year |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL |
Savings: $1,506 Cost: - |
- | - | - | - | - | - | - | - | $1,506 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - lb |
- - $ |
$1,506 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $821 Cost: $3,000 |
$409 | 9,965 | $412 | 48 | - | - | - | - | - | - | - | - | - | - |
$409 9,965 kWh |
$412 48 kW-months/year |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $678 Cost: $713 |
$60 | 1,465 | $618 | 72 | - | - | - | - | - | - | - | - | - | - |
$60 1,465 kWh |
$618 72 kW-months/year |
- - lb |
- - $ |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $160,873 Cost: $152,713 |
$1,490 | 36,342 | $2,677 | 312 | $24,096 | 198,069 | $22,815 | - | $3,298 | - | $6,497 | - | $100,000 | - | $1,490 36,342 kWh |
$2,677 312 kW-months/year |
$24,096 198,069 lb |
$22,815 - $ |
$3,298 - $ |
$6,497 - $ |
$100,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $34,594 Cost: $14,000 |
$1,021 | 24,912 | $1,647 | 192 | - | - | $30,420 | - | $1,506 | - | - | - | - | - | $1,021 24,912 kWh |
$1,647 192 kW-months/year |
- - lb |
$30,420 - $ |
$1,506 - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Raw Material | By-product Production | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Primary Raw Material | By-product Production |