IAC Assessment: TR0007
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: TR0007
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Texas Rio Grande Valley
Assessment Year 2018
Principal Product Grinding Wheels
NAICS 327910 - Abrasive Product Manufacturing
SIC 3291 - Abrasive Products
Sales $50,000,000-$100,000,000
# of Employees 117
Plant Area (Sq.Ft.) 153,578
Annual Production 10,000 Units
Production Hrs. Annual 8,760
Location (State) TX
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $197,815 6,550,320 kWh $0.03
Electricity Demand $103,152 12,867 kW-months/year $8.02
TOTAL ENERGY COSTS $321,040
RECOMMENDED SAVINGS* $69,007 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $61,497
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Water Disposal Electricity Usage Electricity Demand Water Disposal
$ kWh $ kW-months/year $ Tgal
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$34,558
Cost:
$3,000
$34,558 1,144,348 - - - - $34,558
1,144,348
kWh
-
-
kW-months/year
-
-
Tgal
02: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$5,927
Cost:
$22,500
- - $5,927 739 - - -
-
kWh
$5,927
739
kW-months/year
-
-
Tgal
03: 3.5318 RECYCLE FLUORESCENT LAMPS Savings:
$10,606
Cost:
$23,530
$10,606 351,199 - - - - $10,606
351,199
kWh
-
-
kW-months/year
-
-
Tgal
04: 3.4155 METER WASTE WATER Savings:
$6,760
Cost:
$2,650
- - - - $6,760 1,760 -
-
kWh
-
-
kW-months/year
$6,760
1,760
Tgal
05: 2.2523 REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS Savings:
$5,572
Cost:
$500
$5,572 184,521 - - - - $5,572
184,521
kWh
-
-
kW-months/year
-
-
Tgal
06: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$4,304
Cost:
$6,855
$4,304 142,517 - - - - $4,304
142,517
kWh
-
-
kW-months/year
-
-
Tgal
07: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS Savings:
$750
Cost:
$2,212
- - - - $750 195 -
-
kWh
-
-
kW-months/year
$750
195
Tgal
08: 2.2511 INSULATE BARE EQUIPMENT Savings:
$421
Cost:
$38
$421 13,927 - - - - $421
13,927
kWh
-
-
kW-months/year
-
-
Tgal
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$109
Cost:
$195
$109 3,614 - - - - $109
3,614
kWh
-
-
kW-months/year
-
-
Tgal
TOTAL RECOMMENDED Savings:
$69,007
Cost:
$61,480
$55,570 1,840,125 $5,927 739 $7,510 1,956 $55,570
1,840,125
kWh
$5,927
739
kW-months/year
$7,510
1,956
Tgal
TOTAL IMPLEMENTED Savings:
$61,497
Cost:
$56,618
$55,570 1,840,125 $5,927 739 - - $55,570
1,840,125
kWh
$5,927
739
kW-months/year
-
-
Tgal
Savings
Cost
$ kWh $ kW-months/year $ Tgal
Electricity Usage Electricity Demand Water Disposal Electricity Usage Electricity Demand Water Disposal