Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Texas Rio Grande Valley |
---|---|
Assessment Year | 2023 |
Principal Product | Treat wastewater |
NAICS | 221320 - Sewage Treatment Facilities |
SIC | 4952 - Sewerage Systems |
Sales | $5,000,000-$10,000,000 |
# of Employees | 19 |
Plant Area (Sq.Ft.) | 2,831,000 |
Annual Production | 3,467,500 Thousand Gallons |
Production Hrs. Annual | 8,760 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $313,927 | 8,442,800 | kWh | $0.04 |
Electricity Demand | $136,664 | 15,517 | kW-months/year | $8.81 |
Electricity Fees | $91,893 | - | $ | - |
TOTAL ENERGY COSTS | $542,484 | |||
RECOMMENDED SAVINGS* | $125,900 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Electricity Usage | Electricity Demand | Electricity Fees | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY |
Savings: $104,742 Cost: $1,421,000 |
$72,046 | 1,937,627 | $32,696 | 3,712 | - | - |
$72,046 1,937,627 kWh |
$32,696 3,712 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4131 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY |
Savings: $10,236 Cost: $21,298 |
$7,734 | 208,023 | $2,502 | 285 | - | - |
$7,734 208,023 kWh |
$2,502 285 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $10,922 Cost: $2,500 |
- | - | - | - | $10,922 | - |
- - kWh |
- - kW-months/year |
$10,922 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $125,900 Cost: $1,444,798 |
$79,781 | 2,145,650 | $35,198 | 3,997 | $10,922 | - | $79,781 2,145,650 kWh |
$35,198 3,997 kW-months/year |
$10,922 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Electricity Usage | Electricity Demand | Electricity Fees |