Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Tennessee Technological University |
---|---|
Assessment Year | 2008 |
Principal Product | Non-woven Fabric Treatment |
NAICS | 313320 - Fabric Coating Mills |
SIC | 2295 - Coated Fabrics, Not Rubberized |
Sales | $10,000,000-$50,000,000 |
# of Employees | 83 |
Plant Area (Sq.Ft.) | 105,000 |
Annual Production | 53,750,000 Pounds |
Production Hrs. Annual | 7,800 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $253,294 | 5,950,000 | kWh | $0.04 |
Electricity Demand | $133,273 | 10,599 | kW-months/year | $12.57 |
Electricity Fees | $12,940 | - | $ | - |
Natural Gas | $1,254,172 | 148,112 | MMBtu | $8.47 |
Fuel Oil #2 | $26,006 | 2,683 | MMBtu | $9.69 |
TOTAL ENERGY COSTS | $1,679,685 | |||
RECOMMENDED SAVINGS* | $368,046 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $53,446 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2427 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT INCOMING FLUIDS |
Savings: $314,600 Cost: $100,000 |
- | - | - | - | $314,600 | 36,761 | - | - |
- - kWh |
- - kW-months/year |
$314,600 36,761 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) |
Savings: $33,000 Cost: $1,000 |
- | - | - | - | - | - | $33,000 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$33,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $18,809 Cost: $22,423 |
$13,448 | 314,496 | $5,361 | 432 | - | - | - | - |
$13,448 314,496 kWh |
$5,361 432 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,637 Cost: $5,950 |
$743 | 17,411 | $894 | 72 | - | - | - | - |
$743 17,411 kWh |
$894 72 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $368,046 Cost: $129,373 |
$14,191 | 331,907 | $6,255 | 504 | $314,600 | 36,761 | $33,000 | - | $14,191 331,907 kWh |
$6,255 504 kW-months/year |
$314,600 36,761 MMBtu |
$33,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $53,446 Cost: $29,373 |
$14,191 | 331,907 | $6,255 | 504 | - | - | $33,000 | - | $14,191 331,907 kWh |
$6,255 504 kW-months/year |
- - MMBtu |
$33,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes |