Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Tennessee Technological University |
---|---|
Assessment Year | 2008 |
Principal Product | Automotive Headliners |
NAICS | 336360 - Motor Vehicle Seating and Interior Trim Manufacturing |
SIC | 2531 - Public Building & Related Furniture |
Sales | $50,000,000-$100,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 125,000 |
Annual Production | 1,225,000 Pieces |
Production Hrs. Annual | 5,000 |
Location (State) | KY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $371,512 | 11,275,500 | kWh | $0.03 |
Electricity Demand | $274,335 | 23,729 | kW-months/year | $11.56 |
Electricity Fees | $136,521 | - | $ | - |
Natural Gas | $23,246 | 1,600 | MMBtu | $14.53 |
TOTAL ENERGY COSTS | $805,614 | |||
RECOMMENDED SAVINGS* | $1,092,473 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Administrative Changes | Electricity Usage | Electricity Demand | Electricity Fees | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $65,250 Cost: $256,400 |
$31,200 | 843,840 | $20,450 | 1,688 | - | - | $13,600 | - |
$31,200 843,840 kWh |
$20,450 1,688 kW-months/year |
- - $ |
$13,600 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $10,060 Cost: $10,060 |
$4,600 | 124,848 | $3,030 | 250 | - | - | $2,430 | - |
$4,600 124,848 kWh |
$3,030 250 kW-months/year |
- - $ |
$2,430 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $6,360 Cost: $12,000 |
$3,000 | 81,168 | $1,960 | 162 | - | - | $1,400 | - |
$3,000 81,168 kWh |
$1,960 162 kW-months/year |
- - $ |
$1,400 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,930 Cost: $10,100 |
$2,530 | 68,352 | $1,650 | 136 | - | - | $750 | - |
$2,530 68,352 kWh |
$1,650 136 kW-months/year |
- - $ |
$750 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $920 Cost: $1,500 |
$250 | 6,696 | $160 | 13 | $510 | - | - | - |
$250 6,696 kWh |
$160 13 kW-months/year |
$510 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3414 BURN WASTE TO PRODUCE STEAM TO DRIVE A STEAM TURBINE GENERATOR SET AND USE STEAM EXHAUST FOR HEAT |
Savings: $993,250 Cost: $4,000,000 |
$344,250 | 9,304,000 | $169,000 | 1,163 | - | - | $480,000 | - |
$344,250 9,304,000 kWh |
$169,000 1,163 kW-months/year |
- - $ |
$480,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $4,100 Cost: $2,500 |
$4,100 | 336,737 | - | - | - | - | - | - |
$4,100 336,737 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $2,570 Cost: $2,000 |
$2,570 | 78,846 | - | - | - | - | - | - |
$2,570 78,846 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $5,033 Cost: $23,900 |
- | - | - | - | $5,033 | - | - | - |
- - kWh |
- - kW-months/year |
$5,033 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $1,092,473 Cost: $4,318,460 |
$392,500 | 10,844,487 | $196,250 | 3,412 | $5,543 | - | $498,180 | - | $392,500 10,844,487 kWh |
$196,250 3,412 kW-months/year |
$5,543 - $ |
$498,180 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Administrative Changes | Electricity Usage | Electricity Demand | Electricity Fees | Administrative Changes |