Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Tennessee Technological University |
---|---|
Assessment Year | 2010 |
Principal Product | Mechanical Seals |
NAICS | 339991 - Gasket, Packing, and Sealing Device Manufacturing |
SIC | 3053 - Gaskets, Packing And Sealing Devices |
Sales | $50,000,000-$100,000,000 |
# of Employees | 224 |
Plant Area (Sq.Ft.) | 94,000 |
Annual Production | 1 Pieces |
Production Hrs. Annual | 8,400 |
Location (State) | NC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $277,183 | 7,463,000 | kWh | $0.04 |
Electricity Demand | $155,448 | 55,669 | kW-months/year | $2.79 |
Electricity Fees | $13,456 | - | $ | - |
Natural Gas | $26,054 | 2,171 | MMBtu | $12.00 |
TOTAL ENERGY COSTS | $472,141 | |||
RECOMMENDED SAVINGS* | $62,685 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Administrative Changes | Electricity Usage | Electricity Demand | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,600 Cost: $7,100 |
$2,400 | 63,072 | $900 | 105 | $1,300 | - |
$2,400 63,072 kWh |
$900 105 kW-months/year |
$1,300 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $7,100 Cost: $13,100 |
$4,100 | 106,373 | $1,500 | 177 | $1,500 | - |
$4,100 106,373 kWh |
$1,500 177 kW-months/year |
$1,500 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $31,000 Cost: $128,200 |
$19,500 | 506,304 | $7,000 | 844 | $4,500 | - |
$19,500 506,304 kWh |
$7,000 844 kW-months/year |
$4,500 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $1,685 Cost: $2,500 |
$1,685 | 43,776 | - | - | - | - |
$1,685 43,776 kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $9,680 Cost: $5,000 |
$9,680 | 251,280 | - | - | - | - |
$9,680 251,280 kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $3,445 Cost: $25 |
$3,445 | 89,484 | - | - | - | - |
$3,445 89,484 kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $5,175 Cost: $4,900 |
$5,175 | 134,226 | - | - | - | - |
$5,175 134,226 kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $62,685 Cost: $160,825 |
$45,985 | 1,194,515 | $9,400 | 1,126 | $7,300 | - | $45,985 1,194,515 kWh |
$9,400 1,126 kW-months/year |
$7,300 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Administrative Changes | Electricity Usage | Electricity Demand | Administrative Changes |