Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Tennessee Technological University |
---|---|
Assessment Year | 2014 |
Principal Product | Mustard and Vinegar |
NAICS | 311941 - Mayonnaise, Dressing, and Other Prepared Sauce Manufacturing |
SIC | 2035 - Pickles, Sauces, And Salad Dressings |
Sales | $10,000,000-$50,000,000 |
# of Employees | 79 |
Plant Area (Sq.Ft.) | 110,000 |
Annual Production | 225,120 Thousand Gallons |
Production Hrs. Annual | 6,240 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $325,116 | 5,091,920 | kWh | $0.06 |
Electricity Demand | $119,757 | 9,782 | kW-months/year | $12.24 |
Electricity Fees | $6,978 | - | $ | - |
Natural Gas | $138,943 | 14,333 | MMBtu | $9.69 |
TOTAL ENERGY COSTS | $590,794 | |||
RECOMMENDED SAVINGS* | $15,397 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $11,367 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $11,367 Cost: $1,500 |
- | - | - | - | $11,367 | 1,173 |
- - kWh |
- - kW-months/year |
$11,367 1,173 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $764 Cost: $505 |
- | - | - | - | $764 | 79 |
- - kWh |
- - kW-months/year |
$764 79 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $724 Cost: $1,000 |
$724 | 11,307 | - | - | - | - |
$724 11,307 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $148 Cost: $240 |
$148 | 2,317 | - | - | - | - |
$148 2,317 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $388 Cost: $360 |
$388 | 6,059 | - | - | - | - |
$388 6,059 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $724 Cost: $720 |
$724 | 11,326 | - | - | - | - |
$724 11,326 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,282 Cost: $550 |
$981 | 15,320 | $301 | 25 | - | - |
$981 15,320 kWh |
$301 25 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $15,397 Cost: $4,875 |
$2,965 | 46,329 | $301 | 25 | $12,131 | 1,252 | $2,965 46,329 kWh |
$301 25 kW-months/year |
$12,131 1,252 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $11,367 Cost: $1,500 |
- | - | - | - | $11,367 | 1,173 | - - kWh |
- - kW-months/year |
$11,367 1,173 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |