Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Tennessee Technological University |
---|---|
Assessment Year | 2016 |
Principal Product | Steel Tubes |
NAICS | 331210 - Iron and Steel Pipe and Tube Manufacturing from Purchased Steel |
SIC | 3317 - Steel Pipe And Tubes |
Sales | $50,000,000-$100,000,000 |
# of Employees | 247 |
Plant Area (Sq.Ft.) | 450,000 |
Annual Production | 74,000,000 Units |
Production Hrs. Annual | 4,160 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $339,019 | 8,692,800 | kWh | $0.04 |
Electricity Demand | $262,633 | 23,201 | kW-months/year | $11.32 |
Natural Gas | $61,045 | 8,659 | MMBtu | $7.05 |
TOTAL ENERGY COSTS | $662,697 | |||
RECOMMENDED SAVINGS* | $118,468 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $115,767 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4235 REMOVE OR CLOSE OFF UNNEEDED COMPRESSED AIR LINES |
Savings: $27,451 Cost: $700 |
$27,451 | 703,872 | - | - | - | - | - | - |
$27,451 703,872 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $27,289 Cost: - |
$27,289 | 699,729 | - | - | - | - | - | - |
$27,289 699,729 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $25,771 Cost: $40,000 |
$21,680 | 555,897 | $4,091 | 361 | - | - | - | - |
$21,680 555,897 kWh |
$4,091 361 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $22,587 Cost: $100,037 |
$17,071 | 437,728 | $2,069 | 183 | - | - | $3,447 | - |
$17,071 437,728 kWh |
$2,069 183 kW-months/year |
- - MMBtu |
$3,447 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4225 INSTALL COMMON HEADER ON COMPRESSORS |
Savings: $8,381 Cost: $11,700 |
$8,381 | 214,680 | - | - | - | - | - | - |
$8,381 214,680 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7241 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT |
Savings: $2,293 Cost: $10,800 |
$2,293 | 58,792 | - | - | - | - | - | - |
$2,293 58,792 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $2,241 Cost: $2,500 |
$1,420 | 36,410 | $821 | 73 | - | - | - | - |
$1,420 36,410 kWh |
$821 73 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $2,047 Cost: $1,575 |
$785 | 20,130 | - | - | $1,262 | 179 | - | - |
$785 20,130 kWh |
- - kW-months/year |
$1,262 179 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4151 DEVELOP A REPAIR/REPLACE POLICY |
Savings: $408 Cost: $661 |
$200 | 5,135 | $208 | 18 | - | - | - | - |
$200 5,135 kWh |
$208 18 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $118,468 Cost: $167,973 |
$106,570 | 2,732,373 | $7,189 | 635 | $1,262 | 179 | $3,447 | - | $106,570 2,732,373 kWh |
$7,189 635 kW-months/year |
$1,262 179 MMBtu |
$3,447 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $115,767 Cost: $156,512 |
$104,077 | 2,668,446 | $6,981 | 616 | $1,262 | 179 | $3,447 | - | $104,077 2,668,446 kWh |
$6,981 616 kW-months/year |
$1,262 179 MMBtu |
$3,447 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes |