Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Tennessee Technological University
Assessment Year 2017
Principal Product Axle Assemblies
NAICS 331523 - Nonferrous Metal Die-Casting Foundries
SIC 3363 - Aluminum Die-castings
Sales $100,000,000-$500,000,000
# of Employees 134
Plant Area (Sq.Ft.) 103,000
Annual Production 96,000 Units
Production Hrs. Annual 4,000
Location (State) TN
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $75,964 998,400 kWh $0.08
Electricity Demand $23,154 2,513 kW-months/year $9.21
Natural Gas $7,012 853 MMBtu $8.22
TOTAL ENERGY COSTS $136,130
RECOMMENDED SAVINGS* $45,919 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $37,784
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz)
$ kWh $ kW-months/year $ MMBtu $ lb
01: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS Savings:
$33,156
Cost:
$94,000
- - - - - - $33,156 315,640 -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$33,156
315,640
lb
02: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$4,274
Cost:
$3,000
$4,274 56,160 - - - - - - $4,274
56,160
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
03: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS Savings:
$3,861
Cost:
$10,500
$2,510 32,980 - - $1,351 164 - - $2,510
32,980
kWh
-
-
kW-months/year
$1,351
164
MMBtu
-
-
lb
04: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$3,453
Cost:
$8,274
$3,411 44,822 $42 5 - - - - $3,411
44,822
kWh
$42
5
kW-months/year
-
-
MMBtu
-
-
lb
05: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$1,175
Cost:
$250
$634 8,333 - - $541 66 - - $634
8,333
kWh
-
-
kW-months/year
$541
66
MMBtu
-
-
lb
TOTAL RECOMMENDED Savings:
$45,919
Cost:
$116,024
$10,829 142,295 $42 5 $1,892 230 $33,156 315,640 $10,829
142,295
kWh
$42
5
kW-months/year
$1,892
230
MMBtu
$33,156
315,640
lb
TOTAL IMPLEMENTED Savings:
$37,784
Cost:
$102,524
$4,045 53,155 $42 5 $541 66 $33,156 315,640 $4,045
53,155
kWh
$42
5
kW-months/year
$541
66
MMBtu
$33,156
315,640
lb
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ lb
Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz)