Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Tennessee Technological University |
---|---|
Assessment Year | 2022 |
Principal Product | Exterior Automotive Mirrors |
NAICS | 336111 - Automobile Manufacturing |
SIC | 3711 - Motor Vehicles And Car Bodies |
Sales | $100,000,000-$500,000,000 |
# of Employees | 650 |
Plant Area (Sq.Ft.) | 310,000 |
Annual Production | 32,825,809 Units |
Production Hrs. Annual | 8,400 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $673,037 | 15,873,707 | kWh | $0.04 |
Electricity Demand | $329,942 | 27,282 | kW-months/year | $12.09 |
Natural Gas | $513,573 | 49,773 | MMBtu | $10.32 |
TOTAL ENERGY COSTS | $1,580,599 | |||
RECOMMENDED SAVINGS* | $328,993 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $72,599 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT |
Savings: $197,305 Cost: $1,241,200 |
$152,425 | 3,594,939 | $62,094 | 5,136 | $(-17,214) | (-1,668) | - | - |
$152,425 3,594,939 kWh |
$62,094 5,136 kW-months/year |
$(-17,214) (-1,668) MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $65,016 Cost: $5,000 |
- | - | - | - | $65,016 | 6,300 | - | - |
- - kWh |
- - kW-months/year |
$65,016 6,300 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $51,693 Cost: $8,551 |
- | - | - | - | $51,693 | 5,009 | - | - |
- - kWh |
- - kW-months/year |
$51,693 5,009 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $6,155 Cost: $2,860 |
$6,155 | 145,165 | - | - | - | - | - | - |
$6,155 145,165 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $3,192 Cost: $2,000 |
- | - | $3,192 | 264 | - | - | - | - |
- - kWh |
$3,192 264 kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) |
Savings: $1,707 Cost: $400 |
- | - | - | - | - | - | $1,707 | 281 |
- - kWh |
- - kW-months/year |
- - MMBtu |
$1,707 281 Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $1,084 Cost: $428 |
- | - | - | - | $1,084 | 105 | - | - |
- - kWh |
- - kW-months/year |
$1,084 105 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,072 Cost: $1,926 |
$762 | 17,976 | $310 | 26 | - | - | - | - |
$762 17,976 kWh |
$310 26 kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $780 Cost: $2,250 |
$551 | 13,007 | $229 | 19 | - | - | - | - |
$551 13,007 kWh |
$229 19 kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $633 Cost: $1,500 |
$447 | 10,537 | $186 | 15 | - | - | - | - |
$447 10,537 kWh |
$186 15 kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $356 Cost: $700 |
$356 | 8,400 | - | - | - | - | - | - |
$356 8,400 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $328,993 Cost: $1,266,815 |
$160,696 | 3,790,024 | $66,011 | 5,460 | $100,579 | 9,746 | $1,707 | 281 | $160,696 3,790,024 kWh |
$66,011 5,460 kW-months/year |
$100,579 9,746 MMBtu |
$1,707 281 Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $72,599 Cost: $10,486 |
$7,273 | 171,541 | $310 | 26 | $65,016 | 6,300 | - | - | $7,273 171,541 kWh |
$310 26 kW-months/year |
$65,016 6,300 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal |