Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Tennessee Technological University |
---|---|
Assessment Year | 2022 |
Principal Product | Heaters and Controls |
NAICS | 333414 - Heating Equipment (except Warm Air Furnaces) Manufacturing |
SIC | 3433 - Heating Equipment, Except Electric |
Sales | $50,000,000-$100,000,000 |
# of Employees | 95 |
Plant Area (Sq.Ft.) | 141,000 |
Annual Production | 3,600 Pieces |
Production Hrs. Annual | 4,125 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $126,191 | 2,233,200 | kWh | $0.06 |
Electricity Demand | $114,688 | 6,009 | kW-months/year | $19.09 |
Electricity Fees | $5,680 | - | $ | - |
Natural Gas | $44,314 | 3,445 | MMBtu | $12.86 |
TOTAL ENERGY COSTS | $290,873 | |||
RECOMMENDED SAVINGS* | $38,947 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $15,235 Cost: $8,435 |
$1,985 | 35,138 | - | - | - | - | $13,250 | 1,030 | - | - |
$1,985 35,138 kWh |
- - kW-months/year |
- - $ |
$13,250 1,030 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.212 ADOPT IN-HOUSE MATERIAL GENERATION |
Savings: $11,462 Cost: $31,920 |
$(-425) | (-7,522) | - | - | - | - | - | - | $11,887 | - |
$(-425) (-7,522) kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$11,887 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $2,904 Cost: $3,000 |
$2,904 | 51,402 | - | - | - | - | - | - | - | - |
$2,904 51,402 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,769 Cost: $2,815 |
$2,769 | 49,003 | - | - | - | - | - | - | - | - |
$2,769 49,003 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS |
Savings: $2,371 Cost: $4,045 |
$1,203 | 21,285 | $1,168 | 61 | - | - | - | - | - | - |
$1,203 21,285 kWh |
$1,168 61 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $2,278 Cost: $500 |
- | - | - | - | $2,278 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,278 - $ |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,116 Cost: $2,790 |
$562 | 9,950 | $554 | 29 | - | - | - | - | - | - |
$562 9,950 kWh |
$554 29 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $812 Cost: $1,090 |
$592 | 10,477 | $220 | 12 | - | - | - | - | - | - |
$592 10,477 kWh |
$220 12 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $38,947 Cost: $54,595 |
$9,590 | 169,732 | $1,942 | 102 | $2,278 | - | $13,250 | 1,030 | $11,887 | - | $9,590 169,732 kWh |
$1,942 102 kW-months/year |
$2,278 - $ |
$13,250 1,030 MMBtu |
$11,887 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Ancillary Material Cost |