Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Tennessee Technological University |
---|---|
Assessment Year | 2023 |
Principal Product | drive shafts |
NAICS | 336350 - Motor Vehicle Transmission and Power Train Parts Manufacturing |
SIC | 3714 - Motor Vehicle Parts And Accessories |
Sales | $50,000,000-$100,000,000 |
# of Employees | 225 |
Plant Area (Sq.Ft.) | 140,000 |
Annual Production | 75,000 Pieces |
Production Hrs. Annual | 7,200 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $290,148 | 3,728,000 | kWh | $0.08 |
Electricity Demand | $120,120 | 8,379 | kW-months/year | $14.34 |
Electricity Fees | $7,709 | - | $ | - |
Natural Gas | $18,032 | 1,660 | MMBtu | $10.86 |
TOTAL ENERGY COSTS | $468,852 | |||
RECOMMENDED SAVINGS* | $63,944 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $22,243 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Water Consumption | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Water Consumption | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY |
Savings: $15,705 Cost: $50,300 |
$15,705 | 201,875 | - | - | - | - | - | - | - | - | - | - |
$15,705 201,875 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.4151 MINIMIZE WATER USAGE |
Savings: $10,675 Cost: $240 |
- | - | - | - | - | - | - | - | $7,379 | 547 | $3,296 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$7,379 547 Tgal |
$3,296 - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $8,764 Cost: $13,000 |
- | - | - | - | - | - | $8,764 | 807 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$8,764 807 MMBtu |
- - Tgal |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $8,557 Cost: $3,205 |
$8,557 | 109,993 | - | - | - | - | - | - | - | - | - | - |
$8,557 109,993 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7234 USE HEAT PUMP FOR SPACE CONDITIONING |
Savings: $7,905 Cost: $7,500 |
$7,905 | 101,611 | - | - | - | - | - | - | - | - | - | - |
$7,905 101,611 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7229 AIR CONDITION ONLY SPACE NECESSARY |
Savings: $3,153 Cost: $6,000 |
$1,176 | 15,120 | - | - | - | - | $1,977 | 182 | - | - | - | - |
$1,176 15,120 kWh |
- - kW-months/year |
- - $ |
$1,977 182 MMBtu |
- - Tgal |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,804 Cost: $10,150 |
$2,070 | 26,604 | $734 | 51 | - | - | - | - | - | - | - | - |
$2,070 26,604 kWh |
$734 51 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $2,266 Cost: $3,750 |
- | - | - | - | $2,266 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,266 - $ |
- - MMBtu |
- - Tgal |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $2,087 Cost: $1,600 |
$2,087 | 26,820 | - | - | - | - | - | - | - | - | - | - |
$2,087 26,820 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,028 Cost: $60 |
$2,028 | 26,064 | - | - | - | - | - | - | - | - | - | - |
$2,028 26,064 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $63,944 Cost: $95,805 |
$39,528 | 508,087 | $734 | 51 | $2,266 | - | $10,741 | 989 | $7,379 | 547 | $3,296 | - | $39,528 508,087 kWh |
$734 51 kW-months/year |
$2,266 - $ |
$10,741 989 MMBtu |
$7,379 547 Tgal |
$3,296 - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $22,243 Cost: $23,390 |
$2,070 | 26,604 | $734 | 51 | - | - | $8,764 | 807 | $7,379 | 547 | $3,296 | - | $2,070 26,604 kWh |
$734 51 kW-months/year |
- - $ |
$8,764 807 MMBtu |
$7,379 547 Tgal |
$3,296 - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Water Consumption | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Water Consumption |