Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Tennessee Technological University |
---|---|
Assessment Year | 2025 |
Principal Product | Residential vinyl siding |
NAICS | 326199 - All Other Plastics Product Manufacturing |
SIC | 3089 - Plastics Products, Nec |
Sales | $100,000,000-$500,000,000 |
# of Employees | 275 |
Plant Area (Sq.Ft.) | 270,000 |
Annual Production | 110,000,000 Pounds |
Production Hrs. Annual | 8,400 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,264,048 | 22,605,600 | kWh | $0.06 |
Electricity Demand | $652,739 | 39,163 | kW-months/year | $16.67 |
Natural Gas | $11,073 | 1,072 | MMBtu | $10.33 |
TOTAL ENERGY COSTS | $1,936,369 | |||
RECOMMENDED SAVINGS* | $195,915 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Electricity Fees | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.9113 USE SOLAR HEAT FOR HEAT |
Savings: $49,796 Cost: $276,634 |
$49,796 | 899,224 | - | - | - | - | - | - |
$49,796 899,224 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.611 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE |
Savings: $33,333 Cost: $35,000 |
- | - | - | - | - | - | $33,333 | - |
- - kWh |
- - kW-months/year |
- - $ |
$33,333 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $31,076 Cost: $9,750 |
- | - | - | - | $31,076 | - | - | - |
- - kWh |
- - kW-months/year |
$31,076 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $24,795 Cost: $10,920 |
$17,397 | 310,665 | $7,398 | 444 | - | - | - | - |
$17,397 310,665 kWh |
$7,398 444 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $22,030 Cost: $20,000 |
$22,030 | 393,368 | - | - | - | - | - | - |
$22,030 393,368 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $15,876 Cost: $5,625 |
$15,876 | 283,500 | - | - | - | - | - | - |
$15,876 283,500 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $11,575 Cost: $11,250 |
$11,575 | 206,700 | - | - | - | - | - | - |
$11,575 206,700 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $6,566 Cost: $850 |
$4,606 | 82,247 | $1,960 | 118 | - | - | - | - |
$4,606 82,247 kWh |
$1,960 118 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $868 Cost: $100 |
$868 | 15,503 | - | - | - | - | - | - |
$868 15,503 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $195,915 Cost: $370,129 |
$122,148 | 2,191,207 | $9,358 | 561 | $31,076 | - | $33,333 | - | $122,148 2,191,207 kWh |
$9,358 561 kW-months/year |
$31,076 - $ |
$33,333 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Electricity Fees | One-time Revenue or Avoided Cost |