IAC Assessment: UA0014
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UA0014
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Alabama
Assessment Year 2008
Principal Product Insulation
NAICS 327420 - Gypsum Product Manufacturing
SIC 3275 - Gypsum Products
Sales $10,000,000-$50,000,000
# of Employees 19
Plant Area (Sq.Ft.) 32,000
Annual Production 1,200,000 Pounds
Production Hrs. Annual 3,120
Location (State) AL
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $130,696 1,561,440 kWh $0.08
Electricity Demand $27,824 5,870 kW-months/year $4.74
Natural Gas $26,211 1,678 MMBtu $15.62
TOTAL ENERGY COSTS $184,731
RECOMMENDED SAVINGS* $31,382 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $13,280
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas
$ kWh $ kW-months/year $ MMBtu
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$1,796
Cost:
-
$1,796 21,457 - - - - $1,796
21,457
kWh
-
-
kW-months/year
-
-
MMBtu
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$8,143
Cost:
$1,040
$8,143 92,290 - - - - $8,143
92,290
kWh
-
-
kW-months/year
-
-
MMBtu
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$2,493
Cost:
$2,877
- - - - $2,493 165 -
-
kWh
-
-
kW-months/year
$2,493
165
MMBtu
04: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$5,800
Cost:
$14,850
- - $5,800 1,224 - - -
-
kWh
$5,800
1,224
kW-months/year
-
-
MMBtu
05: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$1,454
Cost:
$591
$1,454 41,039 - - - - $1,454
41,039
kWh
-
-
kW-months/year
-
-
MMBtu
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$3,934
Cost:
$13,520
$3,229 37,089 $705 143 - - $3,229
37,089
kWh
$705
143
kW-months/year
-
-
MMBtu
07: 2.6214 SHUT OFF PILOTS IN STANDBY EQUIPMENT Savings:
$457
Cost:
$72
- - - - $457 30 -
-
kWh
-
-
kW-months/year
$457
30
MMBtu
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,943
Cost:
$1,164
$2,943 35,128 - - - - $2,943
35,128
kWh
-
-
kW-months/year
-
-
MMBtu
09: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$2,288
Cost:
$770
$2,288 26,283 - - - - $2,288
26,283
kWh
-
-
kW-months/year
-
-
MMBtu
10: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$644
Cost:
$700
$531 6,105 $113 23 - - $531
6,105
kWh
$113
23
kW-months/year
-
-
MMBtu
11: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$1,430
Cost:
$952
- - - - $1,430 89 -
-
kWh
-
-
kW-months/year
$1,430
89
MMBtu
TOTAL RECOMMENDED Savings:
$31,382
Cost:
$36,536
$20,384 259,391 $6,618 1,390 $4,380 284 $20,384
259,391
kWh
$6,618
1,390
kW-months/year
$4,380
284
MMBtu
TOTAL IMPLEMENTED Savings:
$13,280
Cost:
$2,655
$11,393 154,786 - - $1,887 119 $11,393
154,786
kWh
-
-
kW-months/year
$1,887
119
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu
Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas