Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Alabama |
---|---|
Assessment Year | 2009 |
Principal Product | Asphalt Mix |
NAICS | 327390 - Other Concrete Product Manufacturing |
SIC | 2951 - Asphalt Paving Mixtures And Blocks |
Sales | $5,000,000-$10,000,000 |
# of Employees | 30 |
Plant Area (Sq.Ft.) | 150,000 |
Annual Production | 350,000 Tons |
Production Hrs. Annual | 2,500 |
Location (State) | AL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $609,636 | 4,942,750 | kWh | $0.12 |
Fuel Oil #6 | $900,000 | 68,500 | MMBtu | $13.14 |
TOTAL ENERGY COSTS | $1,509,636 | |||
RECOMMENDED SAVINGS* | $159,395 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Fuel Oil #6 | Electricity Usage | Fuel Oil #6 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $970 Cost: $700 |
$970 | 7,162 | - | - |
$970 7,162 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $96,325 Cost: $7,930 |
- | - | $96,325 | 7,331 |
- - kWh |
$96,325 7,331 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $570 Cost: $2,548 |
- | - | $570 | 29 |
- - kWh |
$570 29 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1113 REDUCE COMBUSTION AIR FLOW TO OPTIMUM |
Savings: $61,530 Cost: $16,083 |
$23,880 | 176,243 | $37,650 | 3,617 |
$23,880 176,243 kWh |
$37,650 3,617 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $159,395 Cost: $27,261 |
$24,850 | 183,405 | $134,545 | 10,977 | $24,850 183,405 kWh |
$134,545 10,977 MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - - kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Fuel Oil #6 | Electricity Usage | Fuel Oil #6 |