IAC Assessment: UA0182
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UA0182
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Alabama
Assessment Year 2017
Principal Product Hardwood Flooring
NAICS 321918 - Other Millwork (including Flooring)
SIC 2426 - Hardwood Dimension & Flooring Mills
Sales $50,000,000-$100,000,000
# of Employees 235
Plant Area (Sq.Ft.) 200,000
Annual Production 23,000,000 Units
Production Hrs. Annual 4,250
Location (State) AR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $751,602 25,360,333 kWh $0.03
Electricity Demand $647,456 45,363 kW-months/year $14.27
Electricity Fees $99,613 - $ -
Natural Gas $17,511 2,394 MMBtu $7.31
Wood $78,880 144,236 MMBtu $0.55
TOTAL ENERGY COSTS $1,595,062
RECOMMENDED SAVINGS* $197,255 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $67,068
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Wood Electricity Usage Electricity Demand Electricity Fees Natural Gas Wood
$ kWh $ kW-months/year $ $ $ MMBtu $ MMBtu
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$113,456
Cost:
$170,734
$63,986 2,158,769 $42,406 2,971 $7,064 - - - - - $63,986
2,158,769
kWh
$42,406
2,971
kW-months/year
$7,064
-
$
-
-
MMBtu
-
-
MMBtu
02: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$32,696
Cost:
$2,784
$13,519 456,100 $17,138 1,201 $2,039 - - - - - $13,519
456,100
kWh
$17,138
1,201
kW-months/year
$2,039
-
$
-
-
MMBtu
-
-
MMBtu
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$5,380
Cost:
$8,066
$5,045 170,217 - - $335 - - - - - $5,045
170,217
kWh
-
-
kW-months/year
$335
-
$
-
-
MMBtu
-
-
MMBtu
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$1,371
Cost:
$5,551
$1,286 43,372 - - $85 - - - - - $1,286
43,372
kWh
-
-
kW-months/year
$85
-
$
-
-
MMBtu
-
-
MMBtu
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$17,749
Cost:
$2,465
$6,467 218,192 $10,177 713 $1,105 - - - - - $6,467
218,192
kWh
$10,177
713
kW-months/year
$1,105
-
$
-
-
MMBtu
-
-
MMBtu
06: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$8,680
Cost:
$3,125
$8,140 274,617 - - $540 - - - - - $8,140
274,617
kWh
-
-
kW-months/year
$540
-
$
-
-
MMBtu
-
-
MMBtu
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$4,400
Cost:
$500
$2,126 71,743 $2,000 144 $274 - - - - - $2,126
71,743
kWh
$2,000
144
kW-months/year
$274
-
$
-
-
MMBtu
-
-
MMBtu
08: 2.2447 HEAT WATER WITH EXHAUST HEAT Savings:
$10,960
Cost:
$97,000
- - - - - - - - $10,960 20,041 -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
$10,960
20,041
MMBtu
09: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$2,563
Cost:
$4,224
- - - - - - $2,563 350 - - -
-
kWh
-
-
kW-months/year
-
-
$
$2,563
350
MMBtu
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$197,255
Cost:
$294,449
$100,569 3,393,010 $71,721 5,029 $11,442 - $2,563 350 $10,960 20,041 $100,569
3,393,010
kWh
$71,721
5,029
kW-months/year
$11,442
-
$
$2,563
350
MMBtu
$10,960
20,041
MMBtu
TOTAL IMPLEMENTED Savings:
$67,068
Cost:
$20,664
$33,171 1,119,126 $27,315 1,914 $4,019 - $2,563 350 - - $33,171
1,119,126
kWh
$27,315
1,914
kW-months/year
$4,019
-
$
$2,563
350
MMBtu
-
-
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ MMBtu
Electricity Usage Electricity Demand Electricity Fees Natural Gas Wood Electricity Usage Electricity Demand Electricity Fees Natural Gas Wood