Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Alabama |
---|---|
Assessment Year | 2012 |
Principal Product | Automobile Wheels |
NAICS | 336330 - Motor Vehicle Steering and Suspension Components (except Spring) Manufacturing |
SIC | 3714 - Motor Vehicle Parts And Accessories |
Sales | >$500,000,000 |
# of Employees | 370 |
Plant Area (Sq.Ft.) | 360,000 |
Annual Production | 1,400,000 Pieces |
Production Hrs. Annual | 8,256 |
Location (State) | AL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $3,063,920 | 133,213,913 | kWh | $0.02 |
Electricity Demand | $1,936,080 | 193,608 | kW-months/year | $10.00 |
Natural Gas | $396,288 | 132,096 | MMBtu | $3.00 |
TOTAL ENERGY COSTS | $5,396,288 | |||
RECOMMENDED SAVINGS* | $418,020 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $50,436 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $200,861 Cost: $1,600 |
$120,611 | 5,243,958 | $80,250 | 8,025 | - | - |
$120,611 5,243,958 kWh |
$80,250 8,025 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $85,875 Cost: $23,130 |
$50,367 | 2,189,890 | $35,508 | 3,550 | - | - |
$50,367 2,189,890 kWh |
$35,508 3,550 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $50,436 Cost: $2,500 |
$30,866 | 1,342,019 | $19,570 | 1,957 | - | - |
$30,866 1,342,019 kWh |
$19,570 1,957 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $15,748 Cost: $2,000 |
$6,536 | 284,153 | $9,212 | 921 | - | - |
$6,536 284,153 kWh |
$9,212 921 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $42,972 Cost: $54,662 |
- | - | - | - | $42,972 | 14,324 |
- - kWh |
- - kW-months/year |
$42,972 14,324 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $22,128 Cost: $66,849 |
$13,868 | 602,968 | $8,260 | 826 | - | - |
$13,868 602,968 kWh |
$8,260 826 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $418,020 Cost: $150,741 |
$222,248 | 9,662,988 | $152,800 | 15,279 | $42,972 | 14,324 | $222,248 9,662,988 kWh |
$152,800 15,279 kW-months/year |
$42,972 14,324 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $50,436 Cost: $2,500 |
$30,866 | 1,342,019 | $19,570 | 1,957 | - | - | $30,866 1,342,019 kWh |
$19,570 1,957 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |