Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 1982 |
Principal Product | PAINT AND AEROSOL CANS |
NAICS | n/a |
SIC | 2851 - Paints And Allied Products |
Sales | $10,000,000-$50,000,000 |
# of Employees | 50 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 2,000 Thousand Gallons |
Production Hrs. Annual | 2,250 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $81,089 | 1,964,830 | kWh | $0.04 |
Fuel Oil #2 | $25,117 | 10,430 | MMBtu | $2.41 |
TOTAL ENERGY COSTS | $106,206 | |||
RECOMMENDED SAVINGS* | $42,823 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $40,326 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Fuel Oil #2 | Electricity Usage | Natural Gas | Fuel Oil #2 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7133 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE |
Savings: $1,141 Cost: $45 |
$1,141 | 27,550 | - | - | - | - |
$1,141 27,550 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $2,497 Cost: $700 |
$2,497 | 60,375 | - | - | - | - |
$2,497 60,375 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1332 CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS |
Savings: $39,185 Cost: $33,000 |
- | - | $(-59,016) | (-13,413) | $98,201 | 13,748 |
- - kWh |
$(-59,016) (-13,413) MMBtu |
$98,201 13,748 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $42,823 Cost: $33,745 |
$3,638 | 87,925 | $(-59,016) | (-13,413) | $98,201 | 13,748 | $3,638 87,925 kWh |
$(-59,016) (-13,413) MMBtu |
$98,201 13,748 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $40,326 Cost: $33,045 |
$1,141 | 27,550 | $(-59,016) | (-13,413) | $98,201 | 13,748 | $1,141 27,550 kWh |
$(-59,016) (-13,413) MMBtu |
$98,201 13,748 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Fuel Oil #2 | Electricity Usage | Natural Gas | Fuel Oil #2 |