IAC Assessment: UD0208
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UD0208
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Dayton
Assessment Year 1986
Principal Product CENTRIFUGAL SEPARATION EQUIPMENT
NAICS n/a
SIC 3569 - General Industrial Machinery, Nec
Sales $10,000,000-$50,000,000
# of Employees 141
Plant Area (Sq.Ft.) 0
Annual Production 40 Pieces
Production Hrs. Annual 2,500
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $93,910 1,371,043 kWh $0.07
Natural Gas $73,322 14,287 MMBtu $5.13
LPG $3,882 445 MMBtu $8.72
Fuel Oil #2 $18,378 2,758 MMBtu $6.66
TOTAL ENERGY COSTS $189,492
RECOMMENDED SAVINGS* $43,747 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $43,747
#|Description Savings
Cost
Status Electricity Usage Natural Gas Fuel Oil #2 Administrative Changes Electricity Usage Natural Gas Fuel Oil #2 Administrative Changes
$ kWh $ MMBtu $ MMBtu $ $
01: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$31,222
Cost:
$9,000
- - $25,312 5,062 $5,910 1,034 - - -
-
kWh
$25,312
5,062
MMBtu
$5,910
1,034
MMBtu
-
-
$
02: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$1,200
Cost:
$1,200
- - $1,200 240 - - - - -
-
kWh
$1,200
240
MMBtu
-
-
MMBtu
-
-
$
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$6,707
Cost:
$6,500
- - $6,707 1,342 - - - - -
-
kWh
$6,707
1,342
MMBtu
-
-
MMBtu
-
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,618
Cost:
$1,500
$4,259 57,444 $(-729) (-146) - - $1,088 - $4,259
57,444
kWh
$(-729)
(-146)
MMBtu
-
-
MMBtu
$1,088
-
$
TOTAL RECOMMENDED Savings:
$43,747
Cost:
$18,200
$4,259 57,444 $32,490 6,498 $5,910 1,034 $1,088 - $4,259
57,444
kWh
$32,490
6,498
MMBtu
$5,910
1,034
MMBtu
$1,088
-
$
TOTAL IMPLEMENTED Savings:
$43,747
Cost:
$18,200
$4,259 57,444 $32,490 6,498 $5,910 1,034 $1,088 - $4,259
57,444
kWh
$32,490
6,498
MMBtu
$5,910
1,034
MMBtu
$1,088
-
$
Savings
Cost
$ kWh $ MMBtu $ MMBtu $ $
Electricity Usage Natural Gas Fuel Oil #2 Administrative Changes Electricity Usage Natural Gas Fuel Oil #2 Administrative Changes