Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 1988 |
Principal Product | COMP. RIBBONS & PAPER |
NAICS | n/a |
SIC | 3955 - Carbon Paper And Inked Ribbons |
Sales | $10,000,000-$50,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 0 Units |
Production Hrs. Annual | 2,880 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $187,620 | 2,347,304 | kWh | $0.08 |
Natural Gas | $64,608 | 13,716 | MMBtu | $4.71 |
TOTAL ENERGY COSTS | $252,228 | |||
RECOMMENDED SAVINGS* | $20,375 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $18,010 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $1,643 Cost: $1,000 |
$1,643 | - | - | - | - | - |
$1,643 - kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $8,077 Cost: $935 |
$8,217 | 92,028 | $(-816) | (-190) | $676 | - |
$8,217 92,028 kWh |
$(-816) (-190) MMBtu |
$676 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7494 INSTALL STORM WINDOWS AND DOORS |
Savings: $8,290 Cost: $3,000 |
- | - | $8,290 | 1,928 | - | - |
- - kWh |
$8,290 1,928 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $2,365 Cost: $5,000 |
- | - | $2,365 | 550 | - | - |
- - kWh |
$2,365 550 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $20,375 Cost: $9,935 |
$9,860 | 92,028 | $9,839 | 2,288 | $676 | - | $9,860 92,028 kWh |
$9,839 2,288 MMBtu |
$676 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $18,010 Cost: $4,935 |
$9,860 | 92,028 | $7,474 | 1,738 | $676 | - | $9,860 92,028 kWh |
$7,474 1,738 MMBtu |
$676 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |