Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 1991 |
Principal Product | ELECTRIC WELDED TUBING |
NAICS | n/a |
SIC | 3312 - Blast Furnaces And Steel Mills |
Sales | $50,000,000-$100,000,000 |
# of Employees | 390 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 120 Thousand Feet |
Production Hrs. Annual | 5,800 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $536,085 | 10,038,394 | kWh | $0.05 |
Natural Gas | $313,886 | 80,012 | MMBtu | $3.92 |
TOTAL ENERGY COSTS | $849,971 | |||
RECOMMENDED SAVINGS* | $158,917 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3511 USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS |
Savings: $69,034 Cost: - |
$74,034 | - | - | - | $(-5,000) | - |
$74,034 - kWh |
- - MMBtu |
$(-5,000) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2491 USE COOLING AIR WHICH COOLS HOT WORK PIECES FOR SPACE HEATING |
Savings: $37,108 Cost: $90,000 |
- | - | $37,108 | 8,570 | - | - |
- - kWh |
$37,108 8,570 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $3,239 Cost: $2,700 |
- | - | $3,239 | 748 | - | - |
- - kWh |
$3,239 748 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $2,619 Cost: - |
$2,980 | 64,185 | $(-676) | (-156) | $315 | - |
$2,980 64,185 kWh |
$(-676) (-156) MMBtu |
$315 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6232 INSTALL SET-BACK TIMERS |
Savings: $1,077 Cost: - |
$1,391 | 46,307 | $(-489) | (-113) | $175 | - |
$1,391 46,307 kWh |
$(-489) (-113) MMBtu |
$175 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $45,840 Cost: - |
$51,840 | - | - | - | $(-6,000) | - |
$51,840 - kWh |
- - MMBtu |
$(-6,000) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $158,917 Cost: $92,700 |
$130,245 | 110,492 | $39,182 | 9,049 | $(-10,510) | - | $130,245 110,492 kWh |
$39,182 9,049 MMBtu |
$(-10,510) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |