Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 1993 |
Principal Product | printing |
NAICS | n/a |
SIC | 2732 - Book Printing |
Sales | $50,000,000-$100,000,000 |
# of Employees | 450 |
Plant Area (Sq.Ft.) | 120,000 |
Annual Production | 0 Units |
Production Hrs. Annual | 8,500 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $502,893 | 10,553,634 | kWh | $0.05 |
Natural Gas | $131,295 | 29,391 | MMBtu | $4.47 |
TOTAL ENERGY COSTS | $634,188 | |||
RECOMMENDED SAVINGS* | $54,277 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $44,100 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Electricity Usage | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8113 PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER |
Savings: $44,100 Cost: $50,000 |
- | - | $44,100 | - |
- - kWh |
$44,100 - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $5,101 Cost: $3,000 |
$5,101 | 154,455 | - | - |
$5,101 154,455 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,502 Cost: $8,300 |
$3,502 | 54,513 | - | - |
$3,502 54,513 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $1,574 Cost: $400 |
$1,574 | 37,515 | - | - |
$1,574 37,515 kWh |
- - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $54,277 Cost: $61,700 |
$10,177 | 246,483 | $44,100 | - | $10,177 246,483 kWh |
$44,100 - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $44,100 Cost: $50,000 |
- | - | $44,100 | - | - - kWh |
$44,100 - MMBtu |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Electricity Usage | Natural Gas |