IAC Assessment: UD0527
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UD0527
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Dayton
Assessment Year 1997
Principal Product Graphite heat exchangers
NAICS n/a
SIC 3443 - Fabricated Plate Work (boiler Shops)
Sales $10,000,000-$50,000,000
# of Employees 43
Plant Area (Sq.Ft.) 42,000
Annual Production 0 Pieces
Production Hrs. Annual 2,000
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $32,116 783,412 kWh $0.04
Electricity Demand $26,519 2,340 kW-months/year $11.33
Natural Gas $29,063 4,255 MMBtu $6.83
TOTAL ENERGY COSTS $87,698
RECOMMENDED SAVINGS* $15,411 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $9,177
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Water Disposal Administrative Changes Electricity Usage Electricity Demand Natural Gas Water Disposal Administrative Changes
$ kWh $ kW-months/year $ MMBtu $ Tgal $ $
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$9,177
Cost:
$200
$7,569 137,749 $528 32 - - - - $1,080 - $7,569
137,749
kWh
$528
32
kW-months/year
-
-
MMBtu
-
-
Tgal
$1,080
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,800
Cost:
$3,259
$1,370 33,411 $430 264 - - - - - - $1,370
33,411
kWh
$430
264
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
03: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION Savings:
$1,740
Cost:
$3,000
- - - - - - $1,740 224,383 - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$1,740
224,383
Tgal
-
-
$
04: 2.7442 KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE Savings:
$2,694
Cost:
$200
- - - - $2,694 353 - - - - -
-
kWh
-
-
kW-months/year
$2,694
353
MMBtu
-
-
Tgal
-
-
$
TOTAL RECOMMENDED Savings:
$15,411
Cost:
$6,659
$8,939 171,160 $958 296 $2,694 353 $1,740 224,383 $1,080 - $8,939
171,160
kWh
$958
296
kW-months/year
$2,694
353
MMBtu
$1,740
224,383
Tgal
$1,080
-
$
TOTAL IMPLEMENTED Savings:
$9,177
Cost:
$200
$7,569 137,749 $528 32 - - - - $1,080 - $7,569
137,749
kWh
$528
32
kW-months/year
-
-
MMBtu
-
-
Tgal
$1,080
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ $
Electricity Usage Electricity Demand Natural Gas Water Disposal Administrative Changes Electricity Usage Electricity Demand Natural Gas Water Disposal Administrative Changes