Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 1998 |
Principal Product | Aluminum & Cast Iron Automotive Parts |
NAICS | n/a |
SIC | 3365 - Aluminum Foundries |
Sales | $10,000,000-$50,000,000 |
# of Employees | 225 |
Plant Area (Sq.Ft.) | 100,000 |
Annual Production | 8,000,000 Pieces |
Production Hrs. Annual | 7,800 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $225,815 | 10,604,631 | kWh | $0.02 |
Electricity Demand | $271,102 | 19,560 | kW-months/year | $13.86 |
Natural Gas | $24,786 | 5,545 | MMBtu | $4.47 |
TOTAL ENERGY COSTS | $527,583 | |||
RECOMMENDED SAVINGS* | $266,102 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $213,299 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Electricity Usage | Electricity Demand | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.7391 IMPLEMENT A MAINTENANCE PROGRAM TO KEEP RACKS AND TANKS FREE OF RUST, CRACKS, OR CORROSION |
Savings: $211,528 Cost: $50,000 |
- | - | - | - | $211,528 | - |
- - kWh |
- - kW-months/year |
$211,528 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.423 MOVE PRODUCT USING MECHANICAL MEANS |
Savings: $44,426 Cost: $3,000 |
- | - | - | - | $44,426 | - |
- - kWh |
- - kW-months/year |
$44,426 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $8,377 Cost: $(-10,000) |
$3,655 | 171,747 | $3,722 | 264 | $1,000 | - |
$3,655 171,747 kWh |
$3,722 264 kW-months/year |
$1,000 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,771 Cost: $5,737 |
$668 | 31,360 | $1,103 | 80 | - | - |
$668 31,360 kWh |
$1,103 80 kW-months/year |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $266,102 Cost: $48,737 |
$4,323 | 203,107 | $4,825 | 344 | $256,954 | - | $4,323 203,107 kWh |
$4,825 344 kW-months/year |
$256,954 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $213,299 Cost: $55,737 |
$668 | 31,360 | $1,103 | 80 | $211,528 | - | $668 31,360 kWh |
$1,103 80 kW-months/year |
$211,528 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Electricity Usage | Electricity Demand | Personnel Changes |