Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 1999 |
Principal Product | EPS food packaging |
NAICS | n/a |
SIC | 3086 - Plastics Foam Products |
Sales | $10,000,000-$50,000,000 |
# of Employees | 110 |
Plant Area (Sq.Ft.) | 180,000 |
Annual Production | 11,000,000 Pounds |
Production Hrs. Annual | 8,568 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $288,343 | 12,697,245 | kWh | $0.02 |
Electricity Demand | $285,002 | 20,256 | kW-months/year | $14.07 |
Natural Gas | $2,653 | 521 | MMBtu | $5.09 |
TOTAL ENERGY COSTS | $575,998 | |||
RECOMMENDED SAVINGS* | $2,718,025 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $1,545,353 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Primary Product | Increase in Production | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Primary Product | Increase in Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | $ | % | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.441 INSTALL AUTOMATIC PACKING EQUIPMENT |
Savings: $1,501,920 Cost: $1,075,000 |
- | - | - | - | $1,260,000 | - | - | - | - | - | $241,920 | - |
- - kWh |
- - kW-months/year |
$1,260,000 - $ |
- - $ |
- - $ |
$241,920 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 4.131 MODIFY PROCESS TO REDUCE MATERIAL USE/COST |
Savings: $1,154,672 Cost: $1,100,000 |
- | - | - | - | - | - | - | - | $1,154,672 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - $ |
$1,154,672 - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES |
Savings: $32,400 Cost: $90,000 |
- | - | - | - | $5,400 | - | - | - | $27,000 | - | - | - |
- - kWh |
- - kW-months/year |
$5,400 - $ |
- - $ |
$27,000 - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3511 USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS |
Savings: $18,000 Cost: $30,000 |
- | - | - | - | - | - | $18,000 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$18,000 - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $7,855 Cost: $2,508 |
$4,409 | 191,676 | $3,446 | 245 | - | - | - | - | - | - | - | - |
$4,409 191,676 kWh |
$3,446 245 kW-months/year |
- - $ |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,178 Cost: $9,800 |
$1,637 | 77,960 | $1,541 | 109 | - | - | - | - | - | - | - | - |
$1,637 77,960 kWh |
$1,541 109 kW-months/year |
- - $ |
- - $ |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $2,718,025 Cost: $2,307,308 |
$6,046 | 269,636 | $4,987 | 354 | $1,265,400 | - | $18,000 | - | $1,181,672 | - | $241,920 | - | $6,046 269,636 kWh |
$4,987 354 kW-months/year |
$1,265,400 - $ |
$18,000 - $ |
$1,181,672 - $ |
$241,920 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $1,545,353 Cost: $1,177,308 |
$6,046 | 269,636 | $4,987 | 354 | $1,265,400 | - | - | - | $27,000 | - | $241,920 | - | $6,046 269,636 kWh |
$4,987 354 kW-months/year |
$1,265,400 - $ |
- - $ |
$27,000 - $ |
$241,920 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | $ | $ | $ | % | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Primary Product | Increase in Production | Electricity Usage | Electricity Demand | Personnel Changes | Administrative Changes | Primary Product | Increase in Production |