Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 2001 |
Principal Product | Forging |
NAICS | n/a |
SIC | 3462 - Iron And Steel Forgings |
Sales | $10,000,000-$50,000,000 |
# of Employees | 130 |
Plant Area (Sq.Ft.) | 65,000 |
Annual Production | 30,000,000 Pieces |
Production Hrs. Annual | 5,760 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $266,688 | 12,871,012 | kWh | $0.02 |
Electricity Demand | $566,868 | 40,404 | kW-months/year | $14.03 |
Natural Gas | $49,024 | 8,430 | MMBtu | $5.82 |
TOTAL ENERGY COSTS | $882,580 | |||
RECOMMENDED SAVINGS* | $223,989 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $190,594 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Other Liquid (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Other Liquid (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | gal | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.621 USE FIXTURES TO REDUCE MACHINE CHANGEOUT TIMES |
Savings: $90,000 Cost: $111,000 |
- | - | - | - | - | - | $90,000 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - gal |
$90,000 - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $98,016 Cost: $60,000 |
- | - | - | - | $1,044 | - | $21,120 | - | $60,000 | - | $15,852 | - |
- - kWh |
- - kW-months/year |
$1,044 - gal |
$21,120 - $ |
$60,000 - $ |
$15,852 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.5112 REPROCESS SPENT OILS ON SITE FOR RE-USE |
Savings: $20,174 Cost: $3,131 |
- | - | - | - | $20,174 | 636 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$20,174 636 gal |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $10,875 Cost: - |
- | - | $10,875 | 1,032 | - | - | - | - | - | - | - | - |
- - kWh |
$10,875 1,032 kW-months/year |
- - gal |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $2,578 Cost: $695 |
$726 | 34,560 | $1,852 | 132 | - | - | - | - | - | - | - | - |
$726 34,560 kWh |
$1,852 132 kW-months/year |
- - gal |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,273 Cost: $260 |
$532 | 25,344 | $741 | 53 | - | - | - | - | - | - | - | - |
$532 25,344 kWh |
$741 53 kW-months/year |
- - gal |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED |
Savings: $1,073 Cost: - |
$248 | 11,760 | $825 | 59 | - | - | - | - | - | - | - | - |
$248 11,760 kWh |
$825 59 kW-months/year |
- - gal |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $223,989 Cost: $175,086 |
$1,506 | 71,664 | $14,293 | 1,276 | $21,218 | 636 | $111,120 | - | $60,000 | - | $15,852 | - | $1,506 71,664 kWh |
$14,293 1,276 kW-months/year |
$21,218 636 gal |
$111,120 - $ |
$60,000 - $ |
$15,852 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $190,594 Cost: $171,695 |
$726 | 34,560 | $1,852 | 132 | $1,044 | - | $111,120 | - | $60,000 | - | $15,852 | - | $726 34,560 kWh |
$1,852 132 kW-months/year |
$1,044 - gal |
$111,120 - $ |
$60,000 - $ |
$15,852 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | gal | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Other Liquid (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Other Liquid (non-haz) | Personnel Changes | Administrative Changes | Ancillary Material Cost |