IAC logo
IAC Assessment: UD0617
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UD0617
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Dayton
Assessment Year 2001
Principal Product Forging
NAICS n/a
SIC 3462 - Iron And Steel Forgings
Sales $10,000,000-$50,000,000
# of Employees 130
Plant Area (Sq.Ft.) 65,000
Annual Production 30,000,000 Pieces
Production Hrs. Annual 5,760
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $266,688 12,871,012 kWh $0.02
Electricity Demand $566,868 40,404 kW-months/year $14.03
Natural Gas $49,024 8,430 MMBtu $5.82
TOTAL ENERGY COSTS $882,580
RECOMMENDED SAVINGS* $223,989 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $190,594
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Other Liquid (non-haz) Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Other Liquid (non-haz) Personnel Changes Administrative Changes Ancillary Material Cost
$ kWh $ kW-months/year $ gal $ $ $ $ $ $
01: 4.6210 USE FIXTURES TO REDUCE MACHINE CHANGEOUT TIMES Savings:
$90,000
Cost:
$111,000
- - - - - - $90,000 - - - - - -
-
kWh
-
-
kW-months/year
-
-
gal
$90,000
-
$
-
-
$
-
-
$
02: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR Savings:
$98,016
Cost:
$60,000
- - - - $1,044 - $21,120 - $60,000 - $15,852 - -
-
kWh
-
-
kW-months/year
$1,044
-
gal
$21,120
-
$
$60,000
-
$
$15,852
-
$
03: 3.5112 REPROCESS SPENT OILS ON SITE FOR RE-USE Savings:
$20,174
Cost:
$3,131
- - - - $20,174 636 - - - - - - -
-
kWh
-
-
kW-months/year
$20,174
636
gal
-
-
$
-
-
$
-
-
$
04: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$10,875
Cost:
-
- - $10,875 1,032 - - - - - - - - -
-
kWh
$10,875
1,032
kW-months/year
-
-
gal
-
-
$
-
-
$
-
-
$
05: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$2,578
Cost:
$695
$726 34,560 $1,852 132 - - - - - - - - $726
34,560
kWh
$1,852
132
kW-months/year
-
-
gal
-
-
$
-
-
$
-
-
$
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,273
Cost:
$260
$532 25,344 $741 53 - - - - - - - - $532
25,344
kWh
$741
53
kW-months/year
-
-
gal
-
-
$
-
-
$
-
-
$
07: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$1,073
Cost:
-
$248 11,760 $825 59 - - - - - - - - $248
11,760
kWh
$825
59
kW-months/year
-
-
gal
-
-
$
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$223,989
Cost:
$175,086
$1,506 71,664 $14,293 1,276 $21,218 636 $111,120 - $60,000 - $15,852 - $1,506
71,664
kWh
$14,293
1,276
kW-months/year
$21,218
636
gal
$111,120
-
$
$60,000
-
$
$15,852
-
$
TOTAL IMPLEMENTED Savings:
$190,594
Cost:
$171,695
$726 34,560 $1,852 132 $1,044 - $111,120 - $60,000 - $15,852 - $726
34,560
kWh
$1,852
132
kW-months/year
$1,044
-
gal
$111,120
-
$
$60,000
-
$
$15,852
-
$
Savings
Cost
$ kWh $ kW-months/year $ gal $ $ $ $ $ $
Electricity Usage Electricity Demand Other Liquid (non-haz) Personnel Changes Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Other Liquid (non-haz) Personnel Changes Administrative Changes Ancillary Material Cost