Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 2001 |
Principal Product | Metal working, industrial machines and equipment |
NAICS | n/a |
SIC | 3549 - Metalworking Machinery, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 215 |
Plant Area (Sq.Ft.) | 160,000 |
Annual Production | 8,750,000 Pounds |
Production Hrs. Annual | 5,000 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $98,121 | 3,368,200 | kWh | $0.03 |
Electricity Demand | $61,480 | 7,812 | kW-months/year | $7.87 |
Natural Gas | $81,061 | 10,666 | MMBtu | $7.60 |
TOTAL ENERGY COSTS | $257,520 | |||
RECOMMENDED SAVINGS* | $35,596 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $16,141 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Water Disposal | Other Liquid (non-haz) | Other Liquid (haz) | Administrative Changes | Ancillary Material Cost | Primary Product | Electricity Usage | Electricity Demand | Water Disposal | Other Liquid (non-haz) | Other Liquid (haz) | Administrative Changes | Ancillary Material Cost | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | Tgal | $ | gal | $ | gal | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK |
Savings: $12,500 Cost: $2,500 |
- | - | - | - | - | - | - | - | - | - | - | - | - | - | $12,500 | - |
- - kWh |
- - kW-months/year |
- - Tgal |
- - gal |
- - gal |
- - $ |
- - $ |
$12,500 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.5112 REPROCESS SPENT OILS ON SITE FOR RE-USE |
Savings: $9,526 Cost: $3,323 |
- | - | - | - | - | - | - | - | $9,526 | 2,062 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - Tgal |
- - gal |
$9,526 2,062 gal |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.5146 UTILIZE A CENTRAL COOLANT SYSTEM FOR CLEANING AND REUSE OF METAL WORKING FLUID |
Savings: $5,610 Cost: $3,200 |
- | - | - | - | - | - | $3,690 | 941 | - | - | $1,920 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - Tgal |
$3,690 941 gal |
- - gal |
$1,920 - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,574 Cost: $6,830 |
$2,538 | 54,000 | $1,036 | 130 | - | - | - | - | - | - | - | - | - | - | - | - |
$2,538 54,000 kWh |
$1,036 130 kW-months/year |
- - Tgal |
- - gal |
- - gal |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.4114 REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER |
Savings: $2,978 Cost: $9,800 |
$(-544) | (-19,501) | $(-180) | (-23) | $4,202 | 2,868,964 | - | - | - | - | - | - | $(-500) | - | - | - |
$(-544) (-19,501) kWh |
$(-180) (-23) kW-months/year |
$4,202 2,868,964 Tgal |
- - gal |
- - gal |
- - $ |
$(-500) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7145 INSTALL SKYLIGHTS |
Savings: $1,341 Cost: $4,455 |
$711 | 25,476 | $630 | 120 | - | - | - | - | - | - | - | - | - | - | - | - |
$711 25,476 kWh |
$630 120 kW-months/year |
- - Tgal |
- - gal |
- - gal |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $67 Cost: $170 |
$25 | 900 | $42 | 5 | - | - | - | - | - | - | - | - | - | - | - | - |
$25 900 kWh |
$42 5 kW-months/year |
- - Tgal |
- - gal |
- - gal |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $35,596 Cost: $30,278 |
$2,730 | 60,875 | $1,528 | 232 | $4,202 | 2,868,964 | $3,690 | 941 | $9,526 | 2,062 | $1,920 | - | $(-500) | - | $12,500 | - | $2,730 60,875 kWh |
$1,528 232 kW-months/year |
$4,202 2,868,964 Tgal |
$3,690 941 gal |
$9,526 2,062 gal |
$1,920 - $ |
$(-500) - $ |
$12,500 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $16,141 Cost: $9,500 |
$2,563 | 54,900 | $1,078 | 135 | - | - | - | - | - | - | - | - | - | - | $12,500 | - | $2,563 54,900 kWh |
$1,078 135 kW-months/year |
- - Tgal |
- - gal |
- - gal |
- - $ |
- - $ |
$12,500 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | Tgal | $ | gal | $ | gal | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Water Disposal | Other Liquid (non-haz) | Other Liquid (haz) | Administrative Changes | Ancillary Material Cost | Primary Product | Electricity Usage | Electricity Demand | Water Disposal | Other Liquid (non-haz) | Other Liquid (haz) | Administrative Changes | Ancillary Material Cost | Primary Product |