Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 2002 |
Principal Product | Metal heat-treating and plating |
NAICS | n/a |
SIC | 3471 - Plating And Polishing |
Sales | $5,000,000-$10,000,000 |
# of Employees | 75 |
Plant Area (Sq.Ft.) | 53,000 |
Annual Production | 33,600,000 Pieces |
Production Hrs. Annual | 8,400 |
Location (State) | KY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $105,333 | 3,898,476 | kWh | $0.03 |
Electricity Demand | $32,208 | 8,052 | kW-months/year | $4.00 |
Natural Gas | $204,948 | 19,569 | MMBtu | $10.47 |
TOTAL ENERGY COSTS | $460,156 | |||
RECOMMENDED SAVINGS* | $78,711 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $62,178 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.4156 USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE |
Savings: $33,646 Cost: $32,000 |
- | - | - | - | - | - | $33,646 | 806,751 |
- - kWh |
- - kW-months/year |
- - MMBtu |
$33,646 806,751 Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $25,468 Cost: $12,700 |
- | - | - | - | $25,468 | 3,284 | - | - |
- - kWh |
- - kW-months/year |
$25,468 3,284 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7245 USE DIRECT AIR SUPPLY TO EXHAUST HOODS |
Savings: $9,581 Cost: $675 |
- | - | - | - | $9,581 | 1,474 | - | - |
- - kWh |
- - kW-months/year |
$9,581 1,474 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $2,685 Cost: $2,000 |
- | - | - | - | $2,685 | 413 | - | - |
- - kWh |
- - kW-months/year |
$2,685 413 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $2,204 Cost: $3,320 |
- | - | - | - | $2,204 | 339 | - | - |
- - kWh |
- - kW-months/year |
$2,204 339 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,390 Cost: $5,088 |
$1,169 | 40,230 | $221 | 58 | - | - | - | - |
$1,169 40,230 kWh |
$221 58 kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,342 Cost: $61 |
$1,121 | 38,640 | $221 | 55 | - | - | - | - |
$1,121 38,640 kWh |
$221 55 kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $1,092 Cost: - |
- | - | - | - | - | - | $1,092 | 4,280,628 |
- - kWh |
- - kW-months/year |
- - MMBtu |
$1,092 4,280,628 Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $613 Cost: $1,431 |
$512 | 17,640 | $101 | 25 | - | - | - | - |
$512 17,640 kWh |
$101 25 kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7144 INSTALL SPECTRAL REFLECTORS / DELAMP |
Savings: $379 Cost: $499 |
$317 | 10,920 | $62 | 16 | - | - | - | - |
$317 10,920 kWh |
$62 16 kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.5111 CONVERT FROM INDIRECT TO DIRECT FIRED SYSTEMS |
Savings: $311 Cost: $640 |
$244 | 8,400 | $67 | 17 | - | - | - | - |
$244 8,400 kWh |
$67 17 kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $78,711 Cost: $58,414 |
$3,363 | 115,830 | $672 | 171 | $39,938 | 5,510 | $34,738 | 5,087,379 | $3,363 115,830 kWh |
$672 171 kW-months/year |
$39,938 5,510 MMBtu |
$34,738 5,087,379 Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $62,178 Cost: $47,199 |
$317 | 10,920 | $62 | 16 | $28,153 | 3,697 | $33,646 | 806,751 | $317 10,920 kWh |
$62 16 kW-months/year |
$28,153 3,697 MMBtu |
$33,646 806,751 Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal |