Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 2003 |
Principal Product | Machined parts and systems |
NAICS | 333514 - Special Die and Tool, Die Set, Jig, and Fixture Manufacturing |
SIC | 3544 - Special Dies, Tools, Jigs & Fixtures |
Sales | $10,000,000-$50,000,000 |
# of Employees | 90 |
Plant Area (Sq.Ft.) | 70,000 |
Annual Production | 10,000 Pieces |
Production Hrs. Annual | 5,000 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $46,016 | 1,576,800 | kWh | $0.03 |
Electricity Demand | $71,974 | 5,148 | kW-months/year | $13.98 |
Natural Gas | $9,860 | 1,220 | MMBtu | $8.08 |
TOTAL ENERGY COSTS | $127,850 | |||
RECOMMENDED SAVINGS* | $17,358 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $4,272 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Personnel Changes | Increase in Production | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Personnel Changes | Increase in Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | $ | $ | % | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 4.424 IMPROVE SPACE COMFORT CONDITIONING |
Savings: $4,100 Cost: $5,938 |
- | - | - | - | - | - | - | - | - | - | $4,100 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - $ |
$4,100 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.2123 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS |
Savings: $4,006 Cost: $2,200 |
- | - | - | - | - | - | $4,006 | 87 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$4,006 87 gal |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $2,950 Cost: $800 |
$750 | 30,000 | - | - | $2,200 | 275 | - | - | - | - | - | - |
$750 30,000 kWh |
- - kW-months/year |
$2,200 275 MMBtu |
- - gal |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4226 USE / PURCHASE OPTIMUM SIZED COMPRESSOR |
Savings: $1,823 Cost: $1,500 |
$810 | 30,000 | $1,013 | 6 | - | - | - | - | - | - | - | - |
$810 30,000 kWh |
$1,013 6 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $1,817 Cost: - |
- | - | $2,617 | 31 | - | - | - | - | $(-800) | - | - | - |
- - kWh |
$2,617 31 kW-months/year |
- - MMBtu |
- - gal |
$(-800) - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $971 Cost: $800 |
- | - | $971 | 69 | - | - | - | - | - | - | - | - |
- - kWh |
$971 69 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $541 Cost: $2,030 |
$203 | 7,500 | $338 | 2 | - | - | - | - | - | - | - | - |
$203 7,500 kWh |
$338 2 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $365 Cost: - |
$162 | 6,000 | $203 | 1 | - | - | - | - | - | - | - | - |
$162 6,000 kWh |
$203 1 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7122 DISCONNECT BALLASTS |
Savings: $328 Cost: $65 |
$146 | 5,400 | $182 | 1 | - | - | - | - | - | - | - | - |
$146 5,400 kWh |
$182 1 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $204 Cost: $549 |
$86 | 3,175 | $118 | 1 | - | - | - | - | - | - | - | - |
$86 3,175 kWh |
$118 1 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $172 Cost: $154 |
$71 | 2,628 | $101 | 1 | - | - | - | - | - | - | - | - |
$71 2,628 kWh |
$101 1 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $81 Cost: - |
- | - | - | - | $81 | 10 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$81 10 MMBtu |
- - gal |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $17,358 Cost: $14,036 |
$2,228 | 84,703 | $5,543 | 112 | $2,281 | 285 | $4,006 | 87 | $(-800) | - | $4,100 | - | $2,228 84,703 kWh |
$5,543 112 kW-months/year |
$2,281 285 MMBtu |
$4,006 87 gal |
$(-800) - $ |
$4,100 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $4,272 Cost: $6,092 |
$71 | 2,628 | $101 | 1 | - | - | - | - | - | - | $4,100 | - | $71 2,628 kWh |
$101 1 kW-months/year |
- - MMBtu |
- - gal |
- - $ |
$4,100 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | $ | $ | % | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Personnel Changes | Increase in Production | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Personnel Changes | Increase in Production |