Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 2006 |
Principal Product | Specialty Organic/Inorganic Chemicals |
NAICS | 325193 - Ethyl Alcohol Manufacturing |
SIC | 2869 - Industrial Organic Chemicals, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 84 |
Plant Area (Sq.Ft.) | 155,480 |
Annual Production | 13,000,000 Pounds |
Production Hrs. Annual | 7,200 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $145,672 | 3,325,728 | kWh | $0.04 |
Electricity Demand | $96,366 | 6,756 | kW-months/year | $14.26 |
Natural Gas | $570,011 | 56,617 | MMBtu | $10.07 |
TOTAL ENERGY COSTS | $812,049 | |||
RECOMMENDED SAVINGS* | $111,624 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $49,318 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $18,706 Cost: - |
- | - | - | - | $18,706 | 1,858 | - | - | - | - |
- - kWh |
- - kW-months/year |
$18,706 1,858 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $15,807 Cost: $34,035 |
$5,482 | 304,563 | $9,814 | 324 | - | - | $511 | - | - | - |
$5,482 304,563 kWh |
$9,814 324 kW-months/year |
- - MMBtu |
$511 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $14,936 Cost: $18,000 |
$14,936 | 266,718 | - | - | - | - | - | - | - | - |
$14,936 266,718 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2424 USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS |
Savings: $11,027 Cost: $30,000 |
- | - | - | - | $11,027 | 1,095 | - | - | - | - |
- - kWh |
- - kW-months/year |
$11,027 1,095 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $10,968 Cost: $500 |
$6,880 | 122,880 | $4,088 | 312 | - | - | - | - | - | - |
$6,880 122,880 kWh |
$4,088 312 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.4155 METER WASTE WATER |
Savings: $10,810 Cost: - |
- | - | - | - | - | - | - | - | $10,810 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
$10,810 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2515 USE OPTIMUM THICKNESS INSULATION |
Savings: $8,710 Cost: $4,000 |
- | - | - | - | $8,710 | 865 | - | - | - | - |
- - kWh |
- - kW-months/year |
$8,710 865 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $7,810 Cost: $4,500 |
$6,340 | 113,290 | $1,470 | 108 | - | - | - | - | - | - |
$6,340 113,290 kWh |
$1,470 108 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2424 USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS |
Savings: $6,163 Cost: $12,326 |
- | - | - | - | $6,163 | 612 | - | - | - | - |
- - kWh |
- - kW-months/year |
$6,163 612 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,746 Cost: $8,200 |
$3,758 | 23,108 | - | - | - | - | - | - | $(-12) | - |
$3,758 23,108 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
$(-12) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,408 Cost: - |
$370 | 20,568 | $1,038 | 36 | - | - | - | - | - | - |
$370 20,568 kWh |
$1,038 36 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.1223 INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) |
Savings: $941 Cost: - |
- | - | - | - | $941 | 93 | - | - | - | - |
- - kWh |
- - kW-months/year |
$941 93 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $592 Cost: - |
$156 | 8,640 | $436 | 12 | - | - | - | - | - | - |
$156 8,640 kWh |
$436 12 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $111,624 Cost: $111,561 |
$37,922 | 859,767 | $16,846 | 792 | $45,547 | 4,523 | $511 | - | $10,798 | - | $37,922 859,767 kWh |
$16,846 792 kW-months/year |
$45,547 4,523 MMBtu |
$511 - $ |
$10,798 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $49,318 Cost: $46,235 |
$9,610 | 348,239 | $10,852 | 360 | $28,357 | 2,816 | $511 | - | $(-12) | - | $9,610 348,239 kWh |
$10,852 360 kW-months/year |
$28,357 2,816 MMBtu |
$511 - $ |
$(-12) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Administrative Changes |