Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 2007 |
Principal Product | Brushroll Products |
NAICS | 339994 - Broom, Brush, and Mop Manufacturing |
SIC | 3991 - Brooms And Brushes |
Sales | $10,000,000-$50,000,000 |
# of Employees | 83 |
Plant Area (Sq.Ft.) | 56,000 |
Annual Production | 3,200,000 Pieces |
Production Hrs. Annual | 4,000 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $193,878 | 1,556,126 | kWh | $0.12 |
Natural Gas | $61,443 | 4,659 | MMBtu | $13.19 |
TOTAL ENERGY COSTS | $255,321 | |||
RECOMMENDED SAVINGS* | $30,128 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $1,484 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $11,208 Cost: $22,275 |
$6,513 | 99,440 | $4,281 | 25 | - | - | $414 | - |
$6,513 99,440 kWh |
$4,281 25 kW-months/year |
- - MMBtu |
$414 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $5,342 Cost: $600 |
- | - | - | - | $5,342 | 405 | - | - |
- - kWh |
- - kW-months/year |
$5,342 405 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,341 Cost: $7,780 |
$3,341 | 51,400 | - | - | - | - | $1,000 | - |
$3,341 51,400 kWh |
- - kW-months/year |
- - MMBtu |
$1,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $3,639 Cost: $8,838 |
$2,281 | 34,832 | $850 | 5 | - | - | $508 | - |
$2,281 34,832 kWh |
$850 5 kW-months/year |
- - MMBtu |
$508 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,830 Cost: $10,000 |
$917 | 14,000 | $603 | 4 | - | - | $310 | - |
$917 14,000 kWh |
$603 4 kW-months/year |
- - MMBtu |
$310 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,180 Cost: - |
$468 | 10,875 | $712 | 3 | - | - | - | - |
$468 10,875 kWh |
$712 3 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,102 Cost: $3,285 |
$665 | 10,152 | $437 | 3 | - | - | - | - |
$665 10,152 kWh |
$437 3 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $1,182 Cost: $1,450 |
- | - | - | - | $1,182 | 90 | - | - |
- - kWh |
- - kW-months/year |
$1,182 90 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7122 DISCONNECT BALLASTS |
Savings: $304 Cost: - |
$120 | 2,808 | $184 | 1 | - | - | - | - |
$120 2,808 kWh |
$184 1 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $30,128 Cost: $54,228 |
$14,305 | 223,507 | $7,067 | 41 | $6,524 | 495 | $2,232 | - | $14,305 223,507 kWh |
$7,067 41 kW-months/year |
$6,524 495 MMBtu |
$2,232 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $1,484 Cost: - |
$588 | 13,683 | $896 | 4 | - | - | - | - | $588 13,683 kWh |
$896 4 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes |