Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 2009 |
Principal Product | Plastic Color Concentrate |
NAICS | 325991 - Custom Compounding of Purchased Resins |
SIC | 3087 - Custom Compound Purchased Resins |
Sales | $10,000,000-$50,000,000 |
# of Employees | 75 |
Plant Area (Sq.Ft.) | 90,000 |
Annual Production | 12,000,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $317,733 | 5,890,500 | kWh | $0.05 |
TOTAL ENERGY COSTS | $357,462 | |||
RECOMMENDED SAVINGS* | $104,192 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $45,764 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $40,310 Cost: - |
$1,747 | 62,400 | - | - | $38,563 | 3,868 | - | - |
$1,747 62,400 kWh |
- - kW-months/year |
$38,563 3,868 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2443 RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR |
Savings: $27,536 Cost: - |
- | - | - | - | $27,536 | 2,762 | - | - |
- - kWh |
- - kW-months/year |
$27,536 2,762 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $17,955 Cost: $43,300 |
$9,415 | 336,240 | $8,540 | 56 | - | - | - | - |
$9,415 336,240 kWh |
$8,540 56 kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2628 UTILIZE A LESS EXPENSIVE COOLING METHOD |
Savings: $4,717 Cost: $11,000 |
$(-268) | (-9,600) | $(-254) | (-10) | - | - | $5,239 | 4,518 |
$(-268) (-9,600) kWh |
$(-254) (-10) kW-months/year |
- - MMBtu |
$5,239 4,518 Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $2,905 Cost: $500 |
$2,905 | 103,740 | - | - | - | - | - | - |
$2,905 103,740 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $2,125 Cost: $300 |
$1,058 | 37,800 | $1,067 | 7 | - | - | - | - |
$1,058 37,800 kWh |
$1,067 7 kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $2,002 Cost: $10,000 |
$2,002 | 37,068 | - | - | - | - | - | - |
$2,002 37,068 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $1,781 Cost: - |
$1,781 | 63,600 | - | - | - | - | - | - |
$1,781 63,600 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,807 Cost: $2,958 |
$974 | 34,781 | $833 | 6 | - | - | - | - |
$974 34,781 kWh |
$833 6 kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,251 Cost: $3,537 |
$656 | 23,413 | $595 | 4 | - | - | - | - |
$656 23,413 kWh |
$595 4 kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $554 Cost: - |
$554 | 19,800 | - | - | - | - | - | - |
$554 19,800 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $481 Cost: $200 |
$252 | 9,000 | $229 | 2 | - | - | - | - |
$252 9,000 kWh |
$229 2 kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $768 Cost: - |
$403 | 14,400 | $365 | 2 | - | - | - | - |
$403 14,400 kWh |
$365 2 kW-months/year |
- - MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $104,192 Cost: $71,795 |
$21,479 | 732,642 | $11,375 | 67 | $66,099 | 6,630 | $5,239 | 4,518 | $21,479 732,642 kWh |
$11,375 67 kW-months/year |
$66,099 6,630 MMBtu |
$5,239 4,518 Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $45,764 Cost: $500 |
$6,836 | 244,140 | $365 | 2 | $38,563 | 3,868 | - | - | $6,836 244,140 kWh |
$365 2 kW-months/year |
$38,563 3,868 MMBtu |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal |