Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 2016 |
Principal Product | All Other Plastics Product Manufacturing |
NAICS | 326199 - All Other Plastics Product Manufacturing |
SIC | 3089 - Plastics Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 110 |
Plant Area (Sq.Ft.) | 206,800 |
Annual Production | 14,000,000 Pounds |
Production Hrs. Annual | 6,048 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $459,142 | 6,253,387 | kWh | $0.07 |
Electricity Demand | $105,387 | 14,292 | kW-months/year | $7.37 |
Electricity Fees | $51,769 | - | $ | - |
Natural Gas | $41,728 | 5,637 | MMBtu | $7.40 |
TOTAL ENERGY COSTS | $661,269 | |||
RECOMMENDED SAVINGS* | $147,832 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $89,455 Cost: - |
- | - | - | - | $89,455 | - | - | - |
- - kWh |
- - kW-months/year |
$89,455 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $15,347 Cost: $8,500 |
- | - | - | - | $15,347 | - | - | - |
- - kWh |
- - kW-months/year |
$15,347 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $5,795 Cost: $690 |
$4,828 | 65,318 | $967 | 130 | - | - | - | - |
$4,828 65,318 kWh |
$967 130 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $9,787 Cost: $1,920 |
$9,244 | 125,077 | - | - | - | - | $543 | - |
$9,244 125,077 kWh |
- - kW-months/year |
- - $ |
$543 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $9,504 Cost: $1,152 |
$7,415 | 100,329 | $1,485 | 199 | - | - | $604 | - |
$7,415 100,329 kWh |
$1,485 199 kW-months/year |
- - $ |
$604 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,151 Cost: - |
$934 | 12,640 | $206 | 28 | - | - | $11 | - |
$934 12,640 kWh |
$206 28 kW-months/year |
- - $ |
$11 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,542 Cost: $1,000 |
$2,951 | 39,929 | $591 | 79 | - | - | - | - |
$2,951 39,929 kWh |
$591 79 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $2,067 Cost: $1,500 |
$1,722 | 23,304 | $345 | 46 | - | - | - | - |
$1,722 23,304 kWh |
$345 46 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $751 Cost: - |
$626 | 8,467 | $125 | 17 | - | - | - | - |
$626 8,467 kWh |
$125 17 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $3,078 Cost: $6,000 |
$2,564 | 34,693 | $514 | 69 | - | - | - | - |
$2,564 34,693 kWh |
$514 69 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $7,355 Cost: $21,500 |
$6,128 | 82,917 | $1,227 | 165 | - | - | - | - |
$6,128 82,917 kWh |
$1,227 165 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $147,832 Cost: $42,262 |
$36,412 | 492,674 | $5,460 | 732 | $104,802 | - | $1,158 | - | $36,412 492,674 kWh |
$5,460 732 kW-months/year |
$104,802 - $ |
$1,158 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Ancillary Material Cost |