Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 2017 |
Principal Product | Precision Machined Components |
NAICS | 331221 - Rolled Steel Shape Manufacturing |
SIC | 3399 - Primary Metal Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 80 |
Plant Area (Sq.Ft.) | 54,000 |
Annual Production | 4,000,000 Units |
Production Hrs. Annual | 7,200 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $226,820 | 3,356,756 | kWh | $0.07 |
Electricity Demand | $59,584 | 7,104 | kW-months/year | $8.39 |
Electricity Fees | $1,439 | - | $ | - |
Natural Gas | $17,879 | 2,167 | MMBtu | $8.25 |
TOTAL ENERGY COSTS | $312,727 | |||
RECOMMENDED SAVINGS* | $46,928 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $16,525 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $452 Cost: $300 |
$337 | 4,988 | $115 | 14 | - | - | - | - | - | - |
$337 4,988 kWh |
$115 14 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7241 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT |
Savings: $7,791 Cost: $211,700 |
$6,650 | 98,545 | $1,141 | 135 | - | - | - | - | - | - |
$6,650 98,545 kWh |
$1,141 135 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $6,226 Cost: $3,000 |
$2,140 | 31,708 | $367 | 44 | $3,719 | 571 | - | - | - | - |
$2,140 31,708 kWh |
$367 44 kW-months/year |
$3,719 571 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7233 USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT |
Savings: $5,906 Cost: $23,600 |
$5,042 | 74,414 | $864 | 102 | - | - | - | - | - | - |
$5,042 74,414 kWh |
$864 102 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1123 INSTALL AUTOMATIC STACK DAMPER |
Savings: $847 Cost: $1,050 |
- | - | - | - | $847 | 130 | - | - | - | - |
- - kWh |
- - kW-months/year |
$847 130 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $9,115 Cost: $20,000 |
$5,442 | 80,640 | $1,134 | 134 | - | - | - | - | $2,539 | - |
$5,442 80,640 kWh |
$1,134 134 kW-months/year |
- - MMBtu |
- - $ |
$2,539 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $7,630 Cost: $8,990 |
$6,608 | 97,936 | - | - | - | - | - | - | $1,022 | - |
$6,608 97,936 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
$1,022 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $5,049 Cost: $17,049 |
$4,178 | 61,920 | $871 | 103 | - | - | - | - | - | - |
$4,178 61,920 kWh |
$871 103 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $2,808 Cost: $5,292 |
$2,324 | 34,440 | $484 | 57 | - | - | - | - | - | - |
$2,324 34,440 kWh |
$484 57 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,104 Cost: $1,000 |
$2,403 | 35,604 | $501 | 59 | - | - | $(-1,800) | - | - | - |
$2,403 35,604 kWh |
$501 59 kW-months/year |
- - MMBtu |
$(-1,800) - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $46,928 Cost: $291,981 |
$35,124 | 520,195 | $5,477 | 649 | $4,566 | 701 | $(-1,800) | - | $3,561 | - | $35,124 520,195 kWh |
$5,477 649 kW-months/year |
$4,566 701 MMBtu |
$(-1,800) - $ |
$3,561 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $16,525 Cost: $221,690 |
$15,661 | 232,085 | $1,642 | 195 | - | - | $(-1,800) | - | $1,022 | - | $15,661 232,085 kWh |
$1,642 195 kW-months/year |
- - MMBtu |
$(-1,800) - $ |
$1,022 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost |