IAC Assessment: UD0990
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UD0990
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Dayton
Assessment Year 2018
Principal Product Tubing
NAICS 331210 - Iron and Steel Pipe and Tube Manufacturing from Purchased Steel
SIC 3317 - Steel Pipe And Tubes
Sales $100,000,000-$500,000,000
# of Employees 169
Plant Area (Sq.Ft.) 300,000
Annual Production 72,610 Tons
Production Hrs. Annual 6,000
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $526,834 6,668,779 kWh $0.08
Electricity Demand $3,142 26,517 kW-months/year $0.12
Electricity Fees $74,845 - $ -
Natural Gas $18,695 2,807 MMBtu $6.66
TOTAL ENERGY COSTS $631,800
RECOMMENDED SAVINGS* $133,216 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Water Disposal Personnel Changes One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Electricity Fees Water Disposal Personnel Changes One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ $ $ Tgal $ $ $ $
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$8,680
Cost:
$4,200
$5,858 74,153 - - - - - - - - $2,822 - $5,858
74,153
kWh
-
-
kW-months/year
-
-
$
-
-
Tgal
-
-
$
$2,822
-
$
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$574
Cost:
$1,000
$8,486 107,424 - - - - - - $(-12,000) - $4,088 - $8,486
107,424
kWh
-
-
kW-months/year
-
-
$
-
-
Tgal
$(-12,000)
-
$
$4,088
-
$
03: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$72,351
Cost:
$48,000
- - - - $72,351 - - - - - - - -
-
kWh
-
-
kW-months/year
$72,351
-
$
-
-
Tgal
-
-
$
-
-
$
04: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) Savings:
$7,458
Cost:
$400
- - - - - - $7,458 629 - - - - -
-
kWh
-
-
kW-months/year
-
-
$
$7,458
629
Tgal
-
-
$
-
-
$
05: 2.4151 DEVELOP A REPAIR/REPLACE POLICY Savings:
$2,774
Cost:
$10,470
$2,766 35,008 $8 70 - - - - - - - - $2,766
35,008
kWh
$8
70
kW-months/year
-
-
$
-
-
Tgal
-
-
$
-
-
$
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$41,379
Cost:
$200,263
$41,254 522,200 $125 1,044 - - - - - - - - $41,254
522,200
kWh
$125
1,044
kW-months/year
-
-
$
-
-
Tgal
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$133,216
Cost:
$264,333
$58,364 738,785 $133 1,114 $72,351 - $7,458 629 $(-12,000) - $6,910 - $58,364
738,785
kWh
$133
1,114
kW-months/year
$72,351
-
$
$7,458
629
Tgal
$(-12,000)
-
$
$6,910
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
Tgal
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ Tgal $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Water Disposal Personnel Changes One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Electricity Fees Water Disposal Personnel Changes One-time Revenue or Avoided Cost