IAC Assessment: UD1041
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UD1041
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Dayton
Assessment Year 2022
Principal Product Car interiors
NAICS 326199 - All Other Plastics Product Manufacturing
SIC 3089 - Plastics Products, Nec
Sales $10,000,000-$50,000,000
# of Employees 226
Plant Area (Sq.Ft.) 320,500
Annual Production 7,744,000 Units
Production Hrs. Annual 6,000
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $580,145 12,317,298 kWh $0.05
Electricity Demand $582,192 29,112 kW-months/year $20.00
Natural Gas $258,070 26,823 MMBtu $9.62
TOTAL ENERGY COSTS $1,440,707
RECOMMENDED SAVINGS* $134,523 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Water Disposal Personnel Changes Electricity Usage Electricity Demand Natural Gas Water Disposal Personnel Changes
$ kWh $ kW-months/year $ MMBtu $ Tgal $ $
01: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) Savings:
$12,355
Cost:
-
- - - - - - $12,355 7,626 - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$12,355
7,626
Tgal
-
-
$
02: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$10,327
Cost:
-
$10,327 219,260 - - - - - - - - $10,327
219,260
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$12,960
Cost:
$604
$7,134 151,474 $5,826 292 - - - - - - $7,134
151,474
kWh
$5,826
292
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$3,702
Cost:
-
$2,038 43,265 $1,664 83 - - - - - - $2,038
43,265
kWh
$1,664
83
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$69,148
Cost:
$18,523
$36,574 776,511 $29,818 1,490 - - - - $2,756 - $36,574
776,511
kWh
$29,818
1,490
kW-months/year
-
-
MMBtu
-
-
Tgal
$2,756
-
$
06: 2.7314 REDUCE VENTILATION AIR Savings:
$26,031
Cost:
$45,000
- - - - $26,031 2,706 - - - - -
-
kWh
-
-
kW-months/year
$26,031
2,706
MMBtu
-
-
Tgal
-
-
$
TOTAL RECOMMENDED Savings:
$134,523
Cost:
$64,127
$56,073 1,190,510 $37,308 1,865 $26,031 2,706 $12,355 7,626 $2,756 - $56,073
1,190,510
kWh
$37,308
1,865
kW-months/year
$26,031
2,706
MMBtu
$12,355
7,626
Tgal
$2,756
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ $
Electricity Usage Electricity Demand Natural Gas Water Disposal Personnel Changes Electricity Usage Electricity Demand Natural Gas Water Disposal Personnel Changes