Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Dayton |
---|---|
Assessment Year | 2023 |
Principal Product | Polymer Sealants |
NAICS | 325211 - Plastics Material and Resin Manufacturing |
SIC | 2891 - Adhesives And Sealants |
Sales | $10,000,000-$50,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 33,000 |
Annual Production | 27,400,000 Units |
Production Hrs. Annual | 6,240 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $107,103 | 2,235,415 | kWh | $0.05 |
Electricity Demand | $40,941 | 6,208 | kW-months/year | $6.59 |
Electricity Fees | $346 | - | $ | - |
Natural Gas | $27,157 | 1,841 | MMBtu | $14.75 |
TOTAL ENERGY COSTS | $182,871 | |||
RECOMMENDED SAVINGS* | $10,319 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $1,152 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes | Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | Tgal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $5,907 Cost: - |
$4,674 | 97,182 | $1,233 | 187 | - | - | - | - |
$4,674 97,182 kWh |
$1,233 187 kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $1,486 Cost: - |
- | - | $1,486 | 225 | - | - | - | - |
- - kWh |
$1,486 225 kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) |
Savings: $705 Cost: $260 |
- | - | - | - | $705 | 120 | - | - |
- - kWh |
- - kW-months/year |
$705 120 Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $727 Cost: $952 |
$575 | 11,966 | $152 | 23 | - | - | - | - |
$575 11,966 kWh |
$152 23 kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $342 Cost: - |
$271 | 5,634 | $71 | 11 | - | - | - | - |
$271 5,634 kWh |
$71 11 kW-months/year |
- - Tgal |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,152 Cost: $2,000 |
$619 | 12,867 | - | - | - | - | $533 | - |
$619 12,867 kWh |
- - kW-months/year |
- - Tgal |
$533 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $10,319 Cost: $3,212 |
$6,139 | 127,649 | $2,942 | 446 | $705 | 120 | $533 | - | $6,139 127,649 kWh |
$2,942 446 kW-months/year |
$705 120 Tgal |
$533 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $1,152 Cost: $2,000 |
$619 | 12,867 | - | - | - | - | $533 | - | $619 12,867 kWh |
- - kW-months/year |
- - Tgal |
$533 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | Tgal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes | Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes |