Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Florida |
---|---|
Assessment Year | 1996 |
Principal Product | Fiberglass Boats |
NAICS | n/a |
SIC | 3732 - Boat Building And Repairing |
Sales | $10,000,000-$50,000,000 |
# of Employees | 152 |
Plant Area (Sq.Ft.) | 250,000 |
Annual Production | 250 Pieces |
Production Hrs. Annual | 5,330 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $91,224 | 1,645,369 | kWh | $0.06 |
Electricity Demand | $22,784 | 4,810 | kW-months/year | $4.74 |
TOTAL ENERGY COSTS | $137,971 | |||
RECOMMENDED SAVINGS* | $42,091 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $11,354 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Solid Waste (haz) | Primary Raw Material | By-product Production | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Solid Waste (haz) | Primary Raw Material | By-product Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $1,365 Cost: - |
$1,143 | 20,809 | $222 | 47 | - | - | - | - | - | - | - | - |
$1,143 20,809 kWh |
$222 47 kW-months/year |
- - lb |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $2,698 Cost: $3,997 |
$2,197 | 39,859 | $501 | 106 | - | - | - | - | - | - | - | - |
$2,197 39,859 kWh |
$501 106 kW-months/year |
- - lb |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL |
Savings: $4,777 Cost: $4,300 |
$3,150 | 57,151 | $1,627 | 343 | - | - | - | - | - | - | - | - |
$3,150 57,151 kWh |
$1,627 343 kW-months/year |
- - lb |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,879 Cost: $1,000 |
$3,879 | 56,272 | - | - | - | - | - | - | - | - | - | - |
$3,879 56,272 kWh |
- - kW-months/year |
- - lb |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER |
Savings: $16,182 Cost: $7,020 |
- | - | - | - | $9,563 | 300,900 | - | - | - | - | $6,619 | - |
- - kWh |
- - kW-months/year |
$9,563 300,900 lb |
- - lb |
- - $ |
$6,619 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.8132 USE LESS TOXIC AND VOLATILE SOLVENT SUBSTITUTES |
Savings: $13,190 Cost: - |
- | - | - | - | - | - | $4,800 | 1,980 | $8,390 | - | - | - |
- - kWh |
- - kW-months/year |
- - lb |
$4,800 1,980 lb |
$8,390 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $42,091 Cost: $16,317 |
$10,369 | 174,091 | $2,350 | 496 | $9,563 | 300,900 | $4,800 | 1,980 | $8,390 | - | $6,619 | - | $10,369 174,091 kWh |
$2,350 496 kW-months/year |
$9,563 300,900 lb |
$4,800 1,980 lb |
$8,390 - $ |
$6,619 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $11,354 Cost: $9,297 |
$9,226 | 153,282 | $2,128 | 449 | - | - | - | - | - | - | - | - | $9,226 153,282 kWh |
$2,128 449 kW-months/year |
- - lb |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Solid Waste (haz) | Primary Raw Material | By-product Production | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Solid Waste (haz) | Primary Raw Material | By-product Production |