Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Florida |
---|---|
Assessment Year | 1999 |
Principal Product | Automotive Parts |
NAICS | n/a |
SIC | 3231 - Products Of Purchased Glass |
Sales | $50,000,000-$100,000,000 |
# of Employees | 490 |
Plant Area (Sq.Ft.) | 280,000 |
Annual Production | 1,645,000 Units |
Production Hrs. Annual | 5,640 |
Location (State) | FL |
View Case Study |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $520,047 | 12,384,232 | kWh | $0.04 |
Electricity Demand | $30,944 | 25,268 | kW-months/year | $1.22 |
Natural Gas | $51,838 | 21,674 | MMBtu | $2.39 |
TOTAL ENERGY COSTS | $602,829 | |||
RECOMMENDED SAVINGS* | $201,332 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $80,658 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,938 Cost: - |
$1,788 | 45,721 | $150 | 96 | - | - | - | - |
$1,788 45,721 kWh |
$150 96 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $1,096 Cost: - |
$857 | 20,516 | $239 | 35 | - | - | - | - |
$857 20,516 kWh |
$239 35 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $25,982 Cost: - |
- | - | - | - | $25,982 | - | - | - |
- - kWh |
- - kW-months/year |
$25,982 - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY |
Savings: $53,580 Cost: - |
- | - | - | - | $53,580 | - | - | - |
- - kWh |
- - kW-months/year |
$53,580 - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 4.521 CLEAR AND RENT EXISTING SPACE |
Savings: $118,736 Cost: - |
- | - | - | - | - | - | $118,736 | - |
- - kWh |
- - kW-months/year |
- - lb |
$118,736 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $201,332 Cost: - |
$2,645 | 66,237 | $389 | 131 | $79,562 | - | $118,736 | - | $2,645 66,237 kWh |
$389 131 kW-months/year |
$79,562 - lb |
$118,736 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $80,658 Cost: - |
$857 | 20,516 | $239 | 35 | $79,562 | - | - | - | $857 20,516 kWh |
$239 35 kW-months/year |
$79,562 - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes |