IAC Assessment: UF0283
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UF0283
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Florida
Assessment Year 2001
Principal Product Military Laser Systems
NAICS n/a
SIC 3699 - Electrical Equipment & Supplies, Nec
Sales $50,000,000-$100,000,000
# of Employees 320
Plant Area (Sq.Ft.) 140,000
Annual Production 600 Pieces
Production Hrs. Annual 8,568
Location (State) FL
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $339,082 6,581,674 kWh $0.05
Electricity Demand $53,786 13,061 kW-months/year $4.12
TOTAL ENERGY COSTS $392,868
RECOMMENDED SAVINGS* $175,261 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $9,745
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Personnel Changes Administrative Changes Ancillary Material Cost Primary Product Electricity Usage Electricity Demand Electricity Fees Personnel Changes Administrative Changes Ancillary Material Cost Primary Product
$ kWh $ kW-months/year $ $ $ $ $ $ $ $ $ $
01: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$1,347
Cost:
$2,485
$1,347 22,454 - - - - - - - - - - - - $1,347
22,454
kWh
-
-
kW-months/year
-
-
$
-
-
$
-
-
$
-
-
$
-
-
$
02: 2.7491 INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS Savings:
$13,166
Cost:
$9,333
$13,166 219,441 - - - - - - - - - - - - $13,166
219,441
kWh
-
-
kW-months/year
-
-
$
-
-
$
-
-
$
-
-
$
-
-
$
03: 2.3112 STORE HEATED/ COOLED WATER FOR USE DURING PEAK DEMAND PERIODS Savings:
$9,278
Cost:
$76,200
- - $9,278 2,292 - - - - - - - - - - -
-
kWh
$9,278
2,292
kW-months/year
-
-
$
-
-
$
-
-
$
-
-
$
-
-
$
04: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$82,496
Cost:
$400
- - - - $82,496 - - - - - - - - - -
-
kWh
-
-
kW-months/year
$82,496
-
$
-
-
$
-
-
$
-
-
$
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,592
Cost:
$1,440
$1,139 21,900 $122 3 - - - - $360 - $971 - - - $1,139
21,900
kWh
$122
3
kW-months/year
-
-
$
-
-
$
$360
-
$
$971
-
$
-
-
$
06: 3.5316 CONTRACT A WOOD PALLET RECYCLING COMPANY Savings:
$720
Cost:
-
- - - - - - - - $720 - - - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
$
$720
-
$
-
-
$
-
-
$
07: 4.811 DEMOLISH OLD BUILDING TO REDUCE TAX AND INSURANCE BILLS Savings:
$59,856
Cost:
$420,000
$22,508 658,322 - - - - $14,500 - - - - - $22,848 - $22,508
658,322
kWh
-
-
kW-months/year
-
-
$
$14,500
-
$
-
-
$
-
-
$
$22,848
-
$
08: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$5,806
Cost:
-
$5,130 98,658 - - - - - - $198 - $478 - - - $5,130
98,658
kWh
-
-
kW-months/year
-
-
$
-
-
$
$198
-
$
$478
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$175,261
Cost:
$509,858
$43,290 1,020,775 $9,400 2,295 $82,496 - $14,500 - $1,278 - $1,449 - $22,848 - $43,290
1,020,775
kWh
$9,400
2,295
kW-months/year
$82,496
-
$
$14,500
-
$
$1,278
-
$
$1,449
-
$
$22,848
-
$
TOTAL IMPLEMENTED Savings:
$9,745
Cost:
$3,925
$7,616 143,012 $122 3 - - - - $558 - $1,449 - - - $7,616
143,012
kWh
$122
3
kW-months/year
-
-
$
-
-
$
$558
-
$
$1,449
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $ $ $ $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Personnel Changes Administrative Changes Ancillary Material Cost Primary Product Electricity Usage Electricity Demand Electricity Fees Personnel Changes Administrative Changes Ancillary Material Cost Primary Product