IAC logo
IAC Assessment: UF0386
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UF0386
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Florida
Assessment Year 2006
Principal Product fire rescue vehicles
NAICS 332999 - All Other Miscellaneous Fabricated Metal Product Manufacturing
SIC 3499 - Fabricated Metal Products, Nec
Sales $50,000,000-$100,000,000
# of Employees 242
Plant Area (Sq.Ft.) 78,500
Annual Production 120 Units
Production Hrs. Annual 5,070
Location (State) FL
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $220,741 2,717,100 kWh $0.08
Electricity Demand $49,269 7,503 kW-months/year $6.57
Natural Gas $49,153 3,102 MMBtu $15.85
TOTAL ENERGY COSTS $319,163
RECOMMENDED SAVINGS* $37,252 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$4,441
Cost:
$4,440
$3,725 45,995 $716 109 - - - - - - $3,725
45,995
kWh
$716
109
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
02: 2.7131 ADD AREA LIGHTING SWITCHES Savings:
$5,721
Cost:
$13,094
$5,721 70,634 - - - - - - - - $5,721
70,634
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
03: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$1,878
Cost:
-
$1,878 23,188 - - - - - - - - $1,878
23,188
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
04: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$1,880
Cost:
$56
$1,577 19,469 $303 46 - - - - - - $1,577
19,469
kWh
$303
46
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
05: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$1,101
Cost:
$1,703
$1,101 13,596 - - - - - - - - $1,101
13,596
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$12,727
Cost:
$1,457
$12,727 128,551 - - - - - - - - $12,727
128,551
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
07: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$811
Cost:
-
$811 10,012 - - - - - - - - $811
10,012
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
08: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE Savings:
$711
Cost:
-
$711 7,178 - - - - - - - - $711
7,178
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
09: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$212
Cost:
-
$97 986 - - - - $42 - $73 - $97
986
kWh
-
-
kW-months/year
-
-
MMBtu
$42
-
$
$73
-
$
10: 2.7292 LOWER CEILING TO REDUCE CONDITIONED SPACE Savings:
$4,883
Cost:
$846
- - - - $4,883 307 - - - - -
-
kWh
-
-
kW-months/year
$4,883
307
MMBtu
-
-
$
-
-
$
11: 2.7232 REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL Savings:
$2,887
Cost:
$24,500
$2,154 26,598 $733 111 - - - - - - $2,154
26,598
kWh
$733
111
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$37,252
Cost:
$46,096
$30,502 346,207 $1,752 266 $4,883 307 $42 - $73 - $30,502
346,207
kWh
$1,752
266
kW-months/year
$4,883
307
MMBtu
$42
-
$
$73
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost