IAC Assessment: UF0424
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: UF0424
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Florida
Assessment Year 2009
Principal Product Dimensioned Lumber
NAICS 321113 - Sawmills
SIC 2421 - Sawmills And Planing Mills, General
Sales $50,000,000-$100,000,000
# of Employees 200
Plant Area (Sq.Ft.) 177,000
Annual Production 180,000,000 Units
Production Hrs. Annual 2,704
Location (State) FL
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $867,717 11,797,340 kWh $0.07
Fuel Oil #1 $121,727 4,140 MMBtu $29.40
TOTAL ENERGY COSTS $989,444
RECOMMENDED SAVINGS* $151,240 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Fuel Oil #1 Personnel Changes One-time Revenue or Avoided Cost Electricity Usage Fuel Oil #1 Personnel Changes One-time Revenue or Avoided Cost
$ kWh $ MMBtu $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$53,117
Cost:
$28,843
$53,117 717,791 - - - - - - $53,117
717,791
kWh
-
-
MMBtu
-
-
$
-
-
$
02: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$151
Cost:
$562
$151 2,047 - - - - - - $151
2,047
kWh
-
-
MMBtu
-
-
$
-
-
$
03: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT Savings:
$11,733
Cost:
$397
$11,733 158,558 - - - - - - $11,733
158,558
kWh
-
-
MMBtu
-
-
$
-
-
$
04: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED Savings:
$2,063
Cost:
$425
$2,063 27,875 - - - - - - $2,063
27,875
kWh
-
-
MMBtu
-
-
$
-
-
$
05: 2.7243 IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS Savings:
$31,025
Cost:
$24,740
- - - - $31,025 - - - -
-
kWh
-
-
MMBtu
$31,025
-
$
-
-
$
06: 2.7423 REDUCE HEAT GAIN BY WINDOW TINTING Savings:
$790
Cost:
$800
$790 10,680 - - - - - - $790
10,680
kWh
-
-
MMBtu
-
-
$
-
-
$
07: 3.5313 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE Savings:
$512
Cost:
$2,500
- - - - - - $512 - -
-
kWh
-
-
MMBtu
-
-
$
$512
-
$
08: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC Savings:
$1,080
Cost:
$512
$48 646 - - $1,032 - - - $48
646
kWh
-
-
MMBtu
$1,032
-
$
-
-
$
09: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$1,732
Cost:
$564
$1,732 23,409 - - - - - - $1,732
23,409
kWh
-
-
MMBtu
-
-
$
-
-
$
10: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE Savings:
$9,752
Cost:
$300
$9,752 131,789 - - - - - - $9,752
131,789
kWh
-
-
MMBtu
-
-
$
-
-
$
11: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$2,525
Cost:
-
$2,525 34,124 - - - - - - $2,525
34,124
kWh
-
-
MMBtu
-
-
$
-
-
$
12: 2.4224 UPGRADE CONTROLS ON COMPRESSORS Savings:
$6,440
Cost:
$6,884
$6,440 87,033 - - - - - - $6,440
87,033
kWh
-
-
MMBtu
-
-
$
-
-
$
13: 2.4224 UPGRADE CONTROLS ON COMPRESSORS Savings:
$14,512
Cost:
$12,272
$14,512 196,115 - - - - - - $14,512
196,115
kWh
-
-
MMBtu
-
-
$
-
-
$
14: 2.8227 ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION Savings:
$13,923
Cost:
-
- - $13,923 559 - - - - -
-
kWh
$13,923
559
MMBtu
-
-
$
-
-
$
15: 2.6125 KEEP EQUIPMENT CLEAN Savings:
$1,885
Cost:
$816
$1,885 25,480 - - - - - - $1,885
25,480
kWh
-
-
MMBtu
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$151,240
Cost:
$79,615
$104,748 1,415,547 $13,923 559 $32,057 - $512 - $104,748
1,415,547
kWh
$13,923
559
MMBtu
$32,057
-
$
$512
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - -
-
kWh
-
-
MMBtu
-
-
$
-
-
$
Savings
Cost
$ kWh $ MMBtu $ $ $ $
Electricity Usage Fuel Oil #1 Personnel Changes One-time Revenue or Avoided Cost Electricity Usage Fuel Oil #1 Personnel Changes One-time Revenue or Avoided Cost