Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Florida |
---|---|
Assessment Year | 2020 |
Principal Product | Reclaimed Water and Bio-Solids |
NAICS | 221320 - Sewage Treatment Facilities |
SIC | 4952 - Sewerage Systems |
Sales | $10,000,000-$50,000,000 |
# of Employees | 24 |
Plant Area (Sq.Ft.) | 767,250 |
Annual Production | 7,439,700 Thousand Gallons |
Production Hrs. Annual | 8,760 |
Location (State) | FL |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,063,061 | 16,988,917 | kWh | $0.06 |
TOTAL ENERGY COSTS | $1,063,061 | |||
RECOMMENDED SAVINGS* | $128,672 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $128,672 |
#|Description |
Savings Cost |
Status | Electricity Usage | Personnel Changes | Primary Raw Material | Electricity Usage | Personnel Changes | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $67,090 Cost: $20,230 |
$67,090 | 1,073,441 | - | - | - | - |
$67,090 1,073,441 kWh |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $51,046 Cost: $88,272 |
$51,046 | 816,732 | - | - | - | - |
$51,046 816,732 kWh |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $10,536 Cost: - |
$9,929 | 158,869 | $359 | - | $248 | - |
$9,929 158,869 kWh |
$359 - $ |
$248 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $128,672 Cost: $108,502 |
$128,065 | 2,049,042 | $359 | - | $248 | - | $128,065 2,049,042 kWh |
$359 - $ |
$248 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $128,672 Cost: $108,502 |
$128,065 | 2,049,042 | $359 | - | $248 | - | $128,065 2,049,042 kWh |
$359 - $ |
$248 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Personnel Changes | Primary Raw Material | Electricity Usage | Personnel Changes | Primary Raw Material |